Possible intervention to manage power system security in South Australia (SA) Region
Possible intervention to manage power system security in South Australia (SA) Region
The synchronous generating units currently expected to be synchronised in SA from 0730 hrs 15/12/2023 will be inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
[EventId:202312141130_review] Prices for interval 14-Dec-2023 11:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1125 hrs on 14 December 2023
PRICES ARE SUBJECT TO REVIEW for trading interval 14-Dec-2023 11:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202312141125_review] Prices for interval 14-Dec-2023 11:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1120 hrs on 14 December 2023
PRICES ARE SUBJECT TO REVIEW for trading interval 14-Dec-2023 11:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202312141120_review] Prices for interval 14-Dec-2023 11:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1115 hrs on 14 December 2023
PRICES ARE SUBJECT TO REVIEW for trading interval 14-Dec-2023 11:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202312141115_review] Prices for interval 14-Dec-2023 11:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1110 hrs on 14 December 2023
PRICES ARE SUBJECT TO REVIEW for trading interval 14-Dec-2023 11:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202312141110_review] Prices for interval 14-Dec-2023 11:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1105 hrs on 14 December 2023
PRICES ARE SUBJECT TO REVIEW for trading interval 14-Dec-2023 11:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202312141105_review] Prices for interval 14-Dec-2023 11:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1100 hrs on 14 December 2023
PRICES ARE SUBJECT TO REVIEW for trading interval 14-Dec-2023 11:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Cancellation - Reclassification of a Non-Credible Contingency Event: Darling Downs Power Station in Queensland Region - 14/12/2023
Cancellation - Reclassification of a Non-Credible Contingency Event: Darling Downs Power Station in Queensland Region - 14/12/2023
Refer to MN 112295
Based on advice from the asset owner, AEMO no longer considers the simultaneous trip of all the generators at Darling Downs Power Station as a credible contingency event.
Therefore AEMO cancels the reclassification as a credible contingency event from 0935 hrs 14/12/2023.
Constraint set Q-DARLING_DOWNS_N-2 invoked from 0745 hrs 14/12/2023 to 0935 hrs 14/12/2023
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Darling Downs Power Station in Queensland Region 14/12/2023
Reclassification of a Non-Credible Contingency Event: Darling Downs Power Station in Queensland Region 14/12/2023
Based on advice from the asset owner, AEMO has declared the simultaneous trip of all the generators at Darling Downs Power Station as a credible contingency event.
AEMO considers the simultaneous trip of those generators to now be more likely.
AEMO has reclassified this as a credible contingency event from 0745 hrs 14/12/2023.
To manage power system security constraint set Q-DARLING_DOWNS_N-2 invoked from 0745 hrs 14/12/2023 until further notice.
Manager NEM Real Time Operations