Filter by category
Filter by Date
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 119462
Direction is cancelled from: 0800 hrs 27/10/2024
Manager NEM Real Time Operations
Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 119414
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Synergen Power Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS at 0800 hrs 27/10/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0905 hrs 27/10/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1405 hrs 27/10/2024 / further notice.
Synergen Power Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 119409
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 0750 hrs 27/10/2024
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0800 hrs 27/10/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0905 hrs 27/10/2024 / further notice.
Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 119443
The updated required actions: Synchronise and follow dispatch targets at 0800 hrs 27/10/2024
The direction update is issued at 0515 hrs 27/10/2024.
Manager NEM Real Time Operations
Cancellation - MSL1- VIC Region on 27/10/2024.
Cancellation - MSL1- VIC Region on 27/10/2024.
The Forecast MSL1 condition in the VIC region advised in AEMO Electricity Market Notice No. 119412 is cancelled at 2030 hrs 26/10/2024.
Manager NEM Real Time Operations
[EventId:202410261530_review] Prices for interval 26-Oct-2024 15:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1525 hrs on 26 October 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 26-Oct-2024 15:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202410261525_review] Prices for interval 26-Oct-2024 15:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1520 hrs on 26 October 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 26-Oct-2024 15:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202410261520_review] Prices for interval 26-Oct-2024 15:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1515 hrs on 26 October 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 26-Oct-2024 15:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202410261515_review] Prices for interval 26-Oct-2024 15:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1510 hrs on 26 October 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 26-Oct-2024 15:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.