PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the VIC Region on 13/02/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following Period:
[1.] From 1430 hrs 13/02/2024 to 1600 hrs 13/02/2024.
The forecast capacity reserve requirement is 562 MW.
The minimum capacity reserve available is 384 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 13/02/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 114528 is cancelled at 1445 hrs 12/02/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 13/02/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1700 hrs 13/02/2024 to 1830 hrs 13/02/2024.
The forecast capacity reserve requirement is 1224 MW.
The minimum capacity reserve available is 1098 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 13/02/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 114503 is cancelled at 0300 hrs 12/02/2024
[No LOR2 condition is currently forecast in the STPASA period.]
Manager NEM RTO
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 13/02/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 114495 has been updated at 1430 hrs 11/02/2024 to the following:
[1.] From 1600 hrs 13/02/2024 to 1630 hrs 13/02/2024.
The forecast capacity reserve requirement is 1211 MW.
The minimum capacity reserve available is 1122 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 13/02/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1600 hrs 13/02/2024 to 1700 hrs 13/02/2024.
The forecast capacity reserve requirement is 1319 MW.
The minimum capacity reserve available is 1056 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Dapto - Marulan 8 Line - NSW region - 08/02/2024
Inter-regional transfer limit variation - Dapto - Marulan 8 Line - NSW region - 08/02/2024
At 1015 hrs 08/02/2024 there was a short notice outage of Dapto - Marulan 8 Line
The following constraint set(s) invoked at 1015 hrs 08/02/2024
N-DTMN_8_15M
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - South Pine SVC - QLD region - 07/02/2024
Inter-regional transfer limit variation - South Pine SVC - QLD region - 07/02/2024
At 1850 hrs 07/02/2024 there was an unplanned outage of the South Pine SVC.
The following constraint set(s) invoked at 1855 hrs 07/02/2024
Q-SP_VC
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Greenbank 275kV SVC - QLD region - 06/02/2024
Inter-regional transfer limit variation - Greenbank 275kV SVC - QLD region - 06/02/2024
At 2102 hrs 06/02/2024 there was an unplanned outage of the Greenbank 275kV SVC
The following constraint set(s) invoked at 2110 hrs 06/02/2024
Q-GB_VC
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations