Filter by category
Filter by Date
Update - Network Augmentation Commissioned - QLD Region - 15/05/2024
Update - Network Augmentation Commissioned - QLD Region - 15/04/2024
Refer Market notice: 115974 and 116446
Guybal Munjan 275 kV Switching Station has been commissioned.
The former Ross - Chalumbin No. 857 and Ross - Chalumbin No. 858 275 kV lines have been replaced with the following lines:
H13 Ross - H93 Guybal Munjan No. 8916 275 kV line
H13 Ross - H93 Guybal Munjan No. 8917 275 kV line
H93 Guybal Munjan - H32 Chalumbin No. 857 275 kV line
H93 Guybal Munjan - H32 Chalumbin No. 858 275 kV line
Manager NEM Real Time Operations
[EventId:202405150640_confirmed] Prices for interval 15-May-2024 06:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0700 hrs on 15 May 2024
PRICES ARE NOW CONFIRMED for trading interval 15-May-2024 06:40.
In accordance with Market Notice 116619 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202405150700_confirmed] Prices for interval 15-May-2024 07:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0700 hrs on 15 May 2024
PRICES ARE NOW CONFIRMED for trading interval 15-May-2024 07:00.
In accordance with Market Notice 116623 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202405150655_confirmed] Prices for interval 15-May-2024 06:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0700 hrs on 15 May 2024
PRICES ARE NOW CONFIRMED for trading interval 15-May-2024 06:55.
In accordance with Market Notice 116622 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202405150650_confirmed] Prices for interval 15-May-2024 06:50 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0700 hrs on 15 May 2024
PRICES ARE NOW CONFIRMED for trading interval 15-May-2024 06:50.
In accordance with Market Notice 116621 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202405150645_confirmed] Prices for interval 15-May-2024 06:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0700 hrs on 15 May 2024
PRICES ARE NOW CONFIRMED for trading interval 15-May-2024 06:45.
In accordance with Market Notice 116620 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202405150635_confirmed] Prices for interval 15-May-2024 06:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0700 hrs on 15 May 2024
PRICES ARE NOW CONFIRMED for trading interval 15-May-2024 06:35.
In accordance with Market Notice 116618 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Cancellation of Actual (LOR1) condition in the Qld Region - 14/05/2024
Cancellation of Actual (LOR1) condition in the Qld region - 14/05/2024
The Actual LOR1 Condition in the Qld Region advised in AEMO Electricity Market Notice No.116615 is cancelled at 1815 hrs 14/05/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD Region on 14/05/2024
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 14/05/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs.
The forecast capacity reserve requirement is 830 MW.
The minimum capacity reserve available is 727 MW.
Manager NEM Real Time Operations