Update - Possible intervention to manage power system security in SA region
Update - Possible intervention to manage power system security in SA region
Refer AEMO Electricity Market Notice 113469
The synchronous generating units currently expected to be synchronised in SA from 0005 hrs 20/01/2024 will be inadequate to maintain a secure operating state in SA .
AEMO estimates that, in the absence of sufficient market response by 1530 hrs 19/01/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 25/01/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113410 has been updated at 1400 hrs 19/01/2024 to the following:
From 1900 hrs to 1930 hrs 25/01/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1258 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 25/01/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1830 hrs to 1900 hrs 25/01/2024.
The forecast capacity reserve requirement is 1252 MW.
The minimum capacity reserve available is 1118 MW.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 22/01/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113409 is cancelled at 1400 hrs 19/01/2024.
AEMO Operations
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 16/01/2024
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 16/01/2024
Refer Market Notice 113322
The AEMO Intervention Event and all associated directions are cancelled from 1800 hrs 19/01/2024
Manager NEM Real Time Operations
Possible intervention to manage power system security in South Australia (SA) Region
Possible intervention to manage power system security in South Australia (SA) Region
The synchronous generating units currently expected to be synchronised in SA from 0130 hrs 20/01/2024 will be inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the QLD region - 18/01/2024
Cancellation of Actual (LOR1) condition in the QLD region - 18/01/2024
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.113424 is cancelled at 1815 hrs 18/01/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 18/01/2024
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 18/01/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1530 hrs.
The Actual LOR1 condition is forecast to exist until 2000 hrs
The capacity reserve requirement is 952 MW
The minimum capacity reserve available is 857 MW
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of the No 3 Leg of Directlink .
The following constraint set was invoked at 1510 hrs 18/01/2024
N-MBTE_1
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations