Update - Non-credible contingency event - SA region - 11/12/2023
Update - Non-credible contingency event - SA region - 11/12/2023
Refer AEMO Electricity Market Notice 112181
At 1554 hrs the remaining Mintaro - Waterloo 132 kV Line was returned to service.
The following constraint set(s) revoked:
S-X-MNWT+CB
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 14/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112179 is cancelled at 1400 hrs 11/12/2023.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 14/12/2023
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1630 hrs 14/12/2023 to 1800 hrs 14/12/2023.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 655 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
NON-CONFORMANCE Region QLD1 Monday, 11 December 2023
NON-CONFORMANCE QLD1 Region Monday, 11 December 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GSTONE5
Duration: 11/12/2023 10:30 to 11/12/2023 10:35
Amount: 15 MW
Constraint: NC-Q_GSTONE5
Auto-generated on behalf of Manager NEM Real Time Operations
Non-credible contingency event - SA region - 11/12/2023
Non-credible contingency event - SA region - 11/12/2023
At 0444 hrs the Mintaro - Waterloo 132 kV Line tripped and the Clare North - Mintaro 132 kV Line tripped at the Mintaro end only.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 09/12/2023
Cancellation of Actual (LOR1) condition in the NSW region - 09/12/2023
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.112137 is cancelled at 1850 hrs 09/12/2023.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Saturday, 9 December 2023
NON-CONFORMANCE NSW1 Region Saturday, 9 December 2023
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BW03
Duration: 09/12/2023 17:50 to 09/12/2023 17:55
Amount: -44 MW
Constraint: NC-N_BW03
Auto-generated on behalf of Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/12/2023
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/12/2023
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1344 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/12/2023
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 112125 is cancelled at 0945 hrs 09/12/2023.
Manager NEM Real Time Operations