Transgrid Project Specification Consultation Report: Managing the risk of circuit breaker failure

18/05/2023
Market Network Service Provider, National Electricity Market
StageProject Specification Consultation Report
ConvenorAEMO NSP
Initiated18/05/2023
Accepting submissions?Yes
Submissions close15/08/2023

Transgrid has published the Project Specification Consultation Report (PSCR) for Managing the risk of circuit breaker failure. Publication of this PSCR represents the first step in the Regulatory Test for Transmission (RIT-T) process.

Circuit breakers are essential for the control and protection of the high voltage network. We have identified 122 circuit breakers on our network that will have reached or be approaching the end of their technical life by 2027/28. The probability of failure for these assets is high and is expected to increase as the assets age. If left unaddressed, this will result in greater unserved energy for consumers, greater safety and environment risk, and greater financial costs associated with emergency repair and replacements.

Given the high population of circuit breakers that have been identified for replacement, we consider it prudent and cost effective to manage this risk through a single asset replacement program. This replacement will help limit the amount of in-service failures that occur (along with the associated interruptions to customer load, and safety and environmental consequences).

In the PSCR Transgrid presented two credible network options that would meet the identified need from a technical, commercial, and project delivery perspective. This PSCR finds that implementation of Option 2 is the preferred option at this draft stage of the RIT-T process. Under Option 2:

  • 55 of the 122 identified circuit breakers will be replaced with a DTCB. For these circuit breakers, the associated current transformers are approaching the end of their technical life.
  • 67 of the 122 identified circuit breakers will be replaced with a LHCB. For these circuit breakers, either replacement with a DTCB is not technically feasible, there is no associated current transformers, or the current transformers have substantial remaining life.

The estimated capital cost of this option is approximately $41.50 million +/- 25 per cent. Transgrid is the proponent of the proposed network project.

Transgrid welcomes written submissions on materials contained in this PSCR. Submissions are due on 15 August 2023.

In accordance with the requirements of the Rules, a summary of the Project Specification Consultation Report is made available on the AEMO website. A copy of the PSCR can be obtained from Transgrid’s website or by emailing regulatory.consultation@transgrid.com.au.

X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm