Market Notices

118526RECLASSIFY CONTINGENCY30/09/2024 01:41:19 AM

Reclassification of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Duration: 30/09/2024 01:41 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
118525SETTLEMENTS RESIDUE29/09/2024 07:00:26 PM

[EventId:202409291900_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 29 September 2024 19:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1900 hrs on 29 September 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 September 2024.

Refer to market notice: 118524

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1900 hrs on 29 September 2024.

This is an AEMO autogenerated Market Notice.
     
118524SETTLEMENTS RESIDUE29/09/2024 06:20:24 PM

[EventId:202409291820_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 29 September 2024 18:20

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1820 hrs on 29 September 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 September 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1820 hrs on 29 September 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
118517PRICES SUBJECT TO REVIEW29/09/2024 05:40:11 PM

[EventId:202409291745_review] Prices for interval 29-Sep-2024 17:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1740 hrs on 29 September 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Sep-2024 17:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118516PRICES SUBJECT TO REVIEW29/09/2024 05:35:18 PM

[EventId:202409291740_review] Prices for interval 29-Sep-2024 17:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1735 hrs on 29 September 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Sep-2024 17:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118515PRICES SUBJECT TO REVIEW29/09/2024 05:30:17 PM

[EventId:202409291735_review] Prices for interval 29-Sep-2024 17:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 29 September 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Sep-2024 17:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118514PRICES SUBJECT TO REVIEW29/09/2024 05:25:20 PM

[EventId:202409291730_review] Prices for interval 29-Sep-2024 17:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1725 hrs on 29 September 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Sep-2024 17:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118513PRICES SUBJECT TO REVIEW29/09/2024 05:20:24 PM

[EventId:202409291725_review] Prices for interval 29-Sep-2024 17:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1720 hrs on 29 September 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Sep-2024 17:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118512PRICES SUBJECT TO REVIEW29/09/2024 05:15:23 PM

[EventId:202409291720_review] Prices for interval 29-Sep-2024 17:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1715 hrs on 29 September 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Sep-2024 17:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     