118482MARKET INTERVENTION27/09/2024 03:17:10 PM

Direction - SA region 27/09/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 27/09/2024

Refer to Market Notice 118455


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1515 hrs 27/09/2024
Type of resource: generating unit
Required actions: synchronise and follow dispatch targets at 0800 hrs 28/09/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 29/09/2024.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
118481MARKET INTERVENTION27/09/2024 03:03:26 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 118457

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 29/09/2024.

The direction update is issued at 1500 hrs 27/09/2024.

Manager NEM Real Time Operations
     
118480MARKET INTERVENTION27/09/2024 03:02:08 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 118477

Direction is cancelled from: 1500 hrs 27/09/2024

Manager NEM Real Time Operations
     
118479MARKET INTERVENTION27/09/2024 02:54:03 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 118476

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1600 hrs 27/09/2024.

The direction update is issued at 1450 hrs 27/09/2024.

Manager NEM Real Time Operations
     
118477MARKET INTERVENTION27/09/2024 02:29:51 PM

Direction - SA region 27/09/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 27/09/2024

In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1430 hrs 27/09/2024
Type of resource: generating unit
Required actions: to remain synchronised and follow dispatch targets at 0000 hrs 28/09/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 29/09/2024.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
118476MARKET INTERVENTION27/09/2024 02:28:25 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 118456

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 29/09/2024.

The direction update is issued at 1430 hrs 27/09/2024.

Manager NEM Real Time Operations
     
118470RESERVE NOTICE26/09/2024 04:31:11 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 118449 has been updated at 1630 hrs to the following:

[1.] From 1630 hrs 26/09/2024 to 1930 hrs 26/09/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is {{LOR_U1.ReserveAvailable:962} MW.

Manager NEM Real Time Operations
     
118457MARKET INTERVENTION26/09/2024 05:00:00 PM

Direction - SA region 26/09/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 26/09/2024

Refer to Market Notice 118455


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1700 hrs 26/09/2024
Type of resource: generating unit
Required actions: synchronise and follow dispatch targets at 0800 hrs 27/09/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1600 hrs 27/09/2024.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
118456MARKET INTERVENTION26/09/2024 04:58:46 PM

Direction - SA region 26/09/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 26/09/2024

Refer to Market Notice 118455


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1700 hrs 26/09/2024
Type of resource: generating unit
Required actions: remain synchronised and follow dispatch targets at 0030 hrs 27/09/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 28/09/2024.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm