118548RESERVE NOTICE01/10/2024 03:10:01 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:

1. From 1730 hrs to 2030 hrs 08/10/2024.
The forecast capacity reserve requirement is 1108 MW.
The minimum capacity reserve available is 668 MW.

2. From 2100 hrs to 2200 hrs 08/10/2024.
The forecast capacity reserve requirement is 1120 MW.
The minimum capacity reserve available is 816 MW.

AEMO Operations
     
118517PRICES SUBJECT TO REVIEW29/09/2024 05:40:11 PM

[EventId:202409291745_review] Prices for interval 29-Sep-2024 17:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1740 hrs on 29 September 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Sep-2024 17:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118516PRICES SUBJECT TO REVIEW29/09/2024 05:35:18 PM

[EventId:202409291740_review] Prices for interval 29-Sep-2024 17:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1735 hrs on 29 September 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Sep-2024 17:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118515PRICES SUBJECT TO REVIEW29/09/2024 05:30:17 PM

[EventId:202409291735_review] Prices for interval 29-Sep-2024 17:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 29 September 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Sep-2024 17:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118514PRICES SUBJECT TO REVIEW29/09/2024 05:25:20 PM

[EventId:202409291730_review] Prices for interval 29-Sep-2024 17:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1725 hrs on 29 September 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Sep-2024 17:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118513PRICES SUBJECT TO REVIEW29/09/2024 05:20:24 PM

[EventId:202409291725_review] Prices for interval 29-Sep-2024 17:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1720 hrs on 29 September 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Sep-2024 17:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118512PRICES SUBJECT TO REVIEW29/09/2024 05:15:23 PM

[EventId:202409291720_review] Prices for interval 29-Sep-2024 17:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1715 hrs on 29 September 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Sep-2024 17:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118507NON-CONFORMANCE29/09/2024 09:05:25 AM

NON-CONFORMANCE Region QLD1 Sunday, 29 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 29 September 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 29/09/2024 08:35 to 29/09/2024 09:05
Amount: -38 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
118506INTER-REGIONAL TRANSFER29/09/2024 03:29:13 AM

Inter-regional transfer limit variation - Stockdill - Upper Tumut 1 330 kV line- NSW region - 29/09/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Stockdill - Upper Tumut 1 330 kV line - NSW region - 29/09/2024

At 0313 hrs 29/09/2024 there was an unplanned outage of Stockdill - Upper Tumut 1 330 kV line.

The following constraint set invoked at 0320 hrs 29/09/2024
N-SDUT_1

This constraint set contains equations with the following interconnectors on the LHS.
V-S-MNSP1
VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     