67568INTER-REGIONAL TRANSFER05/03/2019 11:01:41 AM

Update - Constraint Automation to Manage Power System Security in NSW Region -05/03/2019

AEMO ELECTRICITY MARKET NOTICE

Update - Constraint Automation to Manage Power System Security in NSW Region -05/03/2019

In order to maintain the power system in a secure operating state and manage CA violations in the NSW Region, AEMO has invoked an automated constraint set CA_SPS_4B902E2A from 0845 hrs to 1100 hrs.

This Constraint Set contains equations with the following interconnector on the LHS;

N-Q-MNSP1

Manager NEM Real Time Operations

67567INTER-REGIONAL TRANSFER05/03/2019 09:14:10 AM

Constraint Automation to Manage Power System Security in NSW Region -05/03/2019

AEMO ELECTRICITY MARKET NOTICE

Constraint Automation to Manage Power System Security in NSW Region -05/03/2019

In order to maintain the power system in a secure operating state and manage CA violations in the NSW Region, AEMO has invoked an automated constraint set CA_SPS_4B902E2A from 0845 hrs to 1700 hrs.

This Constraint Set contains equations with the following interconnector on the LHS;

N-Q-MNSP1

Manager NEM Real Time Operations


67566RESERVE NOTICE05/03/2019 10:16:57 AM

RESERVE NOTICE MT PASA PUBLICATION 5 March 2019

The MTPASA result published on 5 March 2019 identifies no Low Reserve Conditions over the next 2 years.

Please note that MTPASA informs the market of potential reliability issues to allow the market to respond in the first instance, potentially avoiding the need for any market intervention or direction from AEMO.

For further information, please refer to:
https://www.aemo.com.au/Electricity/National-Electricity-Market-NEM/Data/Market-Management-System-MMS/Projected-Assessment-of-System-Adequacy

This notice supersedes Market Notice 67400 published on 26 February 2019.

Background
As part of a broader process of implementing the reliability standard, AEMO runs the Medium Term Projected Assessment of System Adequacy (MTPASA) process weekly to forecast expected unserved energy levels over a two year period. If the expected annual unserved energy exceeds the maximum level specified by the Reliability Standard, a Low Reserve Condition is identified.

For more information about how AEMO implements the reliability standard, please view the Reliability Standard Implementation Guidelines (RSIG) available on AEMO's website at
http://www.aemo.com.au/-/media/Files/Stakeholder_Consultation/Consultations/Electricity_Consultations/2016/EAAP/Reliability-Standard-Implementation-Guidelines.pdf

Forecasting
AEMO
67565MARKET INTERVENTION05/03/2019 07:41:18 AM

Possible intervention to manage power system security in South Australia (SA) Region -05/03/2019

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in South Australia (SA) Region -05/03/2019

The synchronous generating units expected to be synchronised in SA from 2400 hrs 05/03/2019 to 0600 hrs 06/03/2019 in Pre-dispatch published at 0700 hrs 05/03/2019 are inadequate to maintain sufficient system strength in SA and hence a secure operating state.

AEMO currently estimates that, in the absence of sufficient market response by 1330 hrs 05/03/2019, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations


67564RECLASSIFY CONTINGENCY04/03/2019 10:14:45 PM

Cancellation of a Non-Credible Contingency Event: Hazelwood - Rowville No.1 220kV line and Hazelwood - Rowville No.2 220kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC1

Lines: Hazelwood - Rowville No.1 220kV and Hazelwood - Rowville No.2 220kV

Cancellation time: 04/03/2019 22:14

Constraint set(s) revoked:
V-HWRO_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 67561

Auto-generated on behalf of Manager NEM Real Time Operations
67563RECLASSIFY CONTINGENCY04/03/2019 08:39:45 PM

Cancellation of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Cancellation time: 04/03/2019 20:39

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 67559

Auto-generated on behalf of Manager NEM Real Time Operations
67562RECLASSIFY CONTINGENCY04/03/2019 07:54:49 PM

Cancellation of a Non-Credible Contingency Event: Dederang - Glenrowan No.1 220 kV line and Dederang - Glenrowan No.3 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC1

Lines: Dederang - Glenrowan No.1 220 kV and Dederang - Glenrowan No.3 220 kV

Cancellation time: 04/03/2019 19:54

Constraint set(s) revoked:
V-DDGN_N-2 Constraint set contains the following interconnector(s) on the left hand side:
V-S-MNSP1
V-SA
VIC1-NSW1


Refer AEMO Electricity Market Notice 67560

Auto-generated on behalf of Manager NEM Real Time Operations
67561RECLASSIFY CONTINGENCY04/03/2019 06:12:56 PM

Reclassification of a Non-Credible Contingency Event: Hazelwood - Rowville No.1 220kV line and Hazelwood - Rowville No.2 220kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Hazelwood - Rowville No.1 220kV and Hazelwood - Rowville No.2 220kV

Duration: 04/03/2019 18:12 until further notice

Constraint set(s) invoked:
V-HWRO_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
67560RECLASSIFY CONTINGENCY04/03/2019 02:53:30 PM

Reclassification of a Non-Credible Contingency Event: Dederang - Glenrowan No.1 220 kV line and Dederang - Glenrowan No.3 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Dederang - Glenrowan No.1 220 kV and Dederang - Glenrowan No.3 220 kV

Duration: 04/03/2019 14:53 until further notice

Constraint set(s) invoked:
V-DDGN_N-2 Constraint set contains the following interconnector(s) on the left hand side:
V-S-MNSP1
V-SA
VIC1-NSW1


Auto-generated on behalf of Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm