54222RESERVE NOTICE05/07/2016 03:04:22 PM

RESERVE NOTICE MT PASA PUBLICATION 05 JULY 2016

AEMO ELECTRICITY MARKET NOTICE

The MT PASA RELIABILITY_LRC results published on 05 July 2016 forecast shows low reserve conditions (LRC) in South Australia for Summer 2016-17 and Summer 2017-18. AEMO will continue to monitor the situation and take appropriate actions, if necessary.

The MT PASA results for the next 12 months are summarised at:
http://www.aemo.com.au/Electricity/Data/Forecast-Supply-and-Demand/Medium-Term-Outlook

This notice supersedes Market Notice 54158 published on 28 June 2016.

Please find the following information on some key inputs used in MT PASA:

Static minimum reserve levels (MRLs) have been specified for QLD, NSW and TAS regions as follows:

QLD: 913 MW
NSW: -1564 MW
TAS: 144 MW

The following optimum shared minimum reserve levels between Victoria and South Australia regions have been specified:

VIC Reserve >= 205.00
5.88 * VIC Reserve + SA Reserve >= 1237.88
1.33 * VIC Reserve + SA Reserve >= 228.00
0.43 * VIC Reserve + SA Reserve >= -40.53
0.23 * VIC Reserve + SA Reserve >= -147.55
SA Reserve >= -368.00

In order to remain consistent with the calculation of the minimum reserve levels, the following interconnector headroom constraints (net import/export limit constraints) have also been applied in MT PASA:

QLD: 0 MW of maximum net import into QLD.
NSW: 330 MW of minimum net export from NSW.
VIC: 940MW of maximum net import into VIC.
SA: 0 MW of maximum net import into SA.

Demand Side Participation included in MT PASA are:

Summer: QLD 156 MW, NSW 422 MW, VIC 245 MW, SA 167 MW and TAS 73 MW

Winter: QLD 156 MW, NSW 422 MW, VIC 185 MW, SA 167 MW and TAS 73 MW

Supply Planning
AEMO
54221RESERVE NOTICE05/07/2016 02:39:12 PM

Update: Forecast Lack Of Reserve Level 1 (LOR1) condition in the South Australia region - STPASA - 7 July 2016

AEMO ELECTRICITY MARKET NOTICE

RE: AEMO Electricity Market Notice No. 54218

NOTICE OF UPDATE
AEMO declares a Forecast LOR1 condition for the South Australia region for the following period(s):

From 07/07/16 1800 hrs to 2100 hrs
The minimum reserve available is 297 MW
The contingency capacity reserve required is 400 MW.

Hitesh Bavarva
Operations Planning
54220RESERVE NOTICE05/07/2016 12:50:09 PM

Forecast Lack of Reserve Level 1 (LOR1) in the SA Region - PDPASA - 06 July 2016

AEMO ELECTRICITY MARKET NOTICE

Forecast Lack of Reserve Level 1 (LOR1) in the SA Region - PDPASA - 06 July 2016

AEMO declares a Forecast LOR1 condition for the SA Region.

From 1800 hrs to 2030 hrs 06 July 2016

The contingency capacity reserve required is 400 MW

The minimum reserve available is 360 MW


Manager NEM Real Time Operations
54219NON-CONFORMANCE05/07/2016 12:15:15 PM

NON-CONFORMANCE Region VIC1 Tuesday, 5 July 2016

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Tuesday, 5 July 2016

AEMO declared a schedule generating unit non-conforming

Unit: MCKAY1
Duration: 05/07/2016 12:10 to 05/07/2016 12:15
Amount: -44 MW
Constraint: NC-V_MCKAY1

Auto-generated on behalf of Manager NEM Real Time Operations
54218RESERVE NOTICE04/07/2016 03:14:22 PM

Update: Forecast Lack Of Reserve Level 1 (LOR1) condition in the South Australia region - STPASA - 7 & 8 July 2016

AEMO ELECTRICITY MARKET NOTICE

RE: AEMO Electricity Market Notice No. 54209

NOTICE OF UPDATE
AEMO declares a Forecast LOR1 condition for the South Australia region for the following period(s):

1. From 07/07/16 1800 hrs to 2100 hrs
The minimum reserve available is 281 MW

2. From 08/07/16 1830 hrs to 1900 hrs
The minimum reserve available is 396 MW.

The contingency capacity reserve required over the above periods of forecast LOR1 conditions is 400 MW.

Hitesh Bavarva
Operations Planning
54217GENERAL NOTICE04/07/2016 01:59:48 PM

Update - Raise Regulation FCAS Increased - 04/07/16

AEMO ELECTRICITY MARKET NOTICE

Update -Variation to FCAS regulation requirements: NEM Global - 04/07/2016.

Refer MN 54216

FCAS Raise regulation requirements were increased to manage time error to within standards.

The following constraints was invoked to manage raise regulation requirements.

F-MAIN_RREG_0350 invoked from 1320 hrs to 1355 hrs.

Manager NEM Real Time Operations
54216GENERAL NOTICE04/07/2016 01:18:31 PM

Update - Raise Regulation FCAS Increased - 04/07/16

AEMO ELECTRICITY MARKET NOTICE

Variation to FCAS regulation requirements: NEM Global - 04/07/2016.

FCAS Raise regulation requirements were increased to manage time error to within standards.

The following constraints was invoked to manage raise regulation requirements.

F-MAIN_RREG_0350 invoked from 1320 hrs.

Manager NEM Real Time Operations
54215INTER-REGIONAL TRANSFER04/07/2016 10:21:15 AM

Inter-regional transfer limit variation South Australia - 04 July 2016

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation South Australia - 04 July 2016

A short notice outage of the Templers No.2 132 kV Transformer in the SA region has occurred at 0955 hrs.

The following constraint set has been invoked for this outage at 1005 hrs

S-X_TPRS+TPDR

The outage constraint set contains the following interconnector on the LHS

V-S-MNSP1

Refer to AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
54214NON-CONFORMANCE04/07/2016 05:45:16 AM

NON-CONFORMANCE Region VIC1 Monday, 4 July 2016

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Monday, 4 July 2016

AEMO declared a schedule generating unit non-conforming

Unit: HWPS3
Duration: 04/07/2016 05:35 to 04/07/2016 05:45
Amount: -10 MW
Constraint: NC-V_HWPS3

Auto-generated on behalf of Manager NEM Real Time Operations