PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the Vic Region on 31/01/2020
The Forecast LOR2 condition in the Vic region advised in AEMO Electricity Market Notice No. 73091 has been updated at 1530 hrs to the following:
From 1530 hrs 31/01/2020 to 1700 hrs 31/01/2020.
The forecast capacity reserve requirement is 1060 MW.
The minimum capacity reserve available is 748 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Ross - Chalumbin No.857 275 kV line and Ross - Chalumbin No.858 275 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Ross - Chalumbin No.857 275 kV and Ross - Chalumbin No.858 275 kV
Cancellation time: 30/01/2020 14:39
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 73095
Auto-generated on behalf of Manager NEM Real Time Operations
Network Augmentation Commissioned - Vic Region - 30/01/2020
A network augmentation has been commissioned in the VIC region as follows:
The Mortlake - Blue Gum 500 kV Line and the Blue Gum 500/220 kV A1 Transformer have been commissioned at 1459 hrs 30/01/20.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 31/01/2020
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 73094 is cancelled at 1430 hrs 30/12/2020.
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Ross - Chalumbin No.857 275 kV line and Ross - Chalumbin No.858 275 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Ross - Chalumbin No.857 275 kV and Ross - Chalumbin No.858 275 kV
Duration: 30/01/2020 13:35 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 31/01/2020
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1600 hrs 31/01/2020 to 1630 hrs 31/01/2020.
The forecast capacity reserve requirement is 1360 MW.
The minimum capacity reserve available is 1301 MW.
Manager NEM Real Time Operations
Correction - PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the Vic Region on 31/01/2020
Correction to MN 73092 end date
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the Vic region for the following period:
From 1700 hrs 31/01/2020 to 1730 hrs 31/01/2020.
The forecast capacity reserve requirement is 1060 MW.
The minimum capacity reserve available is 1016 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the Vic Region on 31/01/2020
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the Vic region for the following period:
From 1700 hrs 31/01/2020 to 1730 hrs 31/12/2020.
The forecast capacity reserve requirement is 1060 MW.
The minimum capacity reserve available is 1016 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the Vic Region on 31/01/2020
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the Vic region for the following period:
From 1530 hrs 31/01/2020 to 1700 hrs 31/01/2020.
The forecast capacity reserve requirement is 916 MW.
The minimum capacity reserve available is 852 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations