59030NON-CONFORMANCE15/08/2017 05:20:13 PM

NON-CONFORMANCE Region NSW1 Tuesday, 15 August 2017

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 15 August 2017

AEMO declared a schedule generating unit non-conforming

Unit: VP6
Duration: 15/08/2017 17:15 to 15/08/2017 17:20
Amount: -136 MW
Constraint: NC-N_VP6

Auto-generated on behalf of Manager NEM Real Time Operations
59029MARKET SYSTEMS15/08/2017 02:42:36 PM

CHG0044388 : Electricity Market Management System - Site Transfer - Completed

Change Number: CHG0044388

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/ Component: EMMS - Reporting

Change Title: Electricity Market Management System - Site Transfer

Change Description:
Transfer Successful

Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
59028RECLASSIFY CONTINGENCY15/08/2017 01:44:37 PM

Reclassification of a Non-Credible Contingency Event: Para -Templers West and the Magill - Torrens Island A 275 kV Lines in the South Australia region

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event: Para -Templers West and the Magill - Torrens Island A 275 kV Lines in the South Australia region due to the severe weather warning for damaging winds that may exceed the rating of the structures of these Lines.

AEMO has reclassified the simultaneous trip of the Para -Templers West and the Magill - Torrens Island A 275 kV Lines as a credible contingency from 1315 hrs 15/08/2017 until further notice.

Manager NEM Real Time Operations
59027RESERVE NOTICE15/08/2017 01:41:39 PM

RESERVE NOTICE MT PASA PUBLICATION 15 August 2017

AEMO ELECTRICITY MARKET NOTICE

The MTPASA result published on 15 August 2017 shows Low Reserve Conditions (LRC) in South Australia for November 2017, Summer 2017-18, March 2018, May 2018, Summer 2018-19, March 2019, and in Victoria for November 2017, Summer 2017-18, March 2018, Summer 2018-19, and March 2019. AEMO will continue to monitor the situation and take appropriate actions, if necessary.

To view the summary of MTPASA results for the next 24 months, visit AEMO's website at http://www.aemo.com.au/Electricity/National-Electricity-Market-NEM/Data-dashboard and click on the 'Medium Term Outlook' tab.

This notice supersedes Market Notice 58977 published on 09 August 2017.

Background
As part of a broader process of implementing the reliability standard, AEMO runs the Medium Term Projected Assessment of System Adequacy (MTPASA) process weekly to forecast capacity reserve conditions over a two year period.
AEMO may apply probabilistic studies such as Energy Adequacy Assessment Projection (EAAP) to confirm the LRC findings of MTPASA before intervening in the market.

For more information about how AEMO implements the reliability standard, please view the Reliability Standard Implementation Guidelines (RSIG) available on AEMO's website at
http://www.aemo.com.au/-/media/Files/Stakeholder_Consultation/Consultations/Electricity_Consultations/2016/EAAP/Reliability-Standard-Implementation-Guidelines.pdf

Supply Planning
AEMO
59026RECLASSIFY CONTINGENCY14/08/2017 10:22:14 AM

Cancellation of the Reclassification of a Non-Credible Contingency Event: Farrell - John Butters 220 kV Line and the Farrell - Rosebery Tee Queenstown - Newton 110 kV Line in Tasmania due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of the Reclassification of a Non-Credible Contingency Event: Farrell - John Butters 220 kV Line and the Farrell - Rosebery Tee Queenstown - Newton 110 kV Line in Tasmania due to Lightning.

Refer AEMO Electricity Market Notice 59025

There is no longer any lightning activity in the vicinity of the Farrell - John Butters 220 kV Line and the Farrell - Rosebery Tee Queenstown - Newton 110 kV Line.
AEMO has cancelled the reclassification of the simultaneous trip of those circuits as a credible contingency event at 0940 hrs 14/08/2017.

Manager NEM Real Time Operations
59025RECLASSIFY CONTINGENCY14/08/2017 08:18:19 AM

Reclassification of a Non-Credible Contingency Event: Farrell - John Butters 220 kV Line and the Farrell - Rosebery Tee Queenstown - Newton 110 kV Line in Tasmania due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event: Farrell - John Butters 220 kV Line and the Farrell - Rosebery Tee Queenstown - Newton 110 kV Line in Tasmania due to Lightning.

Lightning is occurring near the Farrell - John Butters 220 kV Line and the Farrell - Rosebery Tee Queenstown - Newton 110 kV Line.
AEMO considers the simultaneous trip of those circuits to now be more likely.
Therefore AEMO has reclassified this as a credible contingency event from 0815 hrs 14/08/2017 until further notice.

Manager NEM Real Time Operations
59024INTER-REGIONAL TRANSFER14/08/2017 03:12:13 AM

Inter-regional transfer limit variation: Hazelwood - South Morang No.1 500kV Line (VIC) - Voltage Control

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation: Hazelwood - South Morang No.1 500kV Line (VIC) - Voltage Control

The Hazelwood - South Morang No.1 500kV Line has been de-energised to manage voltages in the VIC region.

The following constraint set was invoked at 0310 hrs 14 August 2017.

V-HWSM

The constraint set contains equations with the following interconnectors on the LHS.

T-V-MNSP1
V-S-MNSP1
V-SA
VIC1-NSW1

Refer to AEMO Network Outage Schedule for further details.

Manager NEM Real Time Operations
59023INTER-REGIONAL TRANSFER13/08/2017 11:51:37 AM

Inter regional transfer limit variation: Liddell - Muswellbrook (83) 330 kV line - NSW region

AEMO ELECTRICITY MARKET NOTICE

Inter regional transfer limit variation: Liddell - Muswellbrook (83) 330 kV line - NSW region

The planned outage of the Liddell - Muswellbrook (83) 330 kV line has been completed ahead of the scheduled end time.

Constraint sets N-LDMU_83 and F-N-LDMU_83 revoked at 1145 hrs.

The containt set contains equations with the following interconnectors on the LHS

N-Q-MNSP1
NSW1-QLD1


Manager NEM Real Time Operations
59022PRICES UNCHANGED13/08/2017 10:44:59 AM

[EventId:201708131045_confirmed] Prices for interval 13-Aug-2017 10:45 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1044 hrs on 13 August 2017

PRICES ARE NOW CONFIRMED for dispatch interval 13-Aug-2017 10:45.

In accordance with Market Notice 59020 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.