54891NON-CONFORMANCE11/09/2016 12:55:18 AM

NON-CONFORMANCE Region QLD1 Sunday, 11 September 2016

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 11 September 2016

AEMO declared a schedule generating unit non-conforming

Unit: TARONG#2
Duration: 11/09/2016 00:45 to 11/09/2016 00:55
Amount: -15 MW
Constraint: NC-Q_TARONG#2

Auto-generated on behalf of Manager NEM Real Time Operations
54890RECLASSIFY CONTINGENCY10/09/2016 07:41:12 PM

Cancellation of the Reclassification of a Non-Credible Contingency Event: Tarong - Chinchilla 7183 and 7168 132 kV Lines in Queensland due to Lightnin

AEMO ELECTRICITY MARKET NOTICE

Cancellation of the Reclassification of a Non-Credible Contingency Event: Tarong - Chinchilla 7183 and 7168 132 kV Lines in Queensland due to Lightning.

Refer AEMO Electricity Market Notice 54887

There is no longer any lightning activity in the vicinity of the Tarong - Chinchilla 7183 and 7168 132 kV Lines.
AEMO has cancelled the reclassification of the simultaneous trip of those circuits as a credible contingency event at 1940 hrs, 10/09/16

Manager NEM Real Time Operations
54889RESERVE NOTICE10/09/2016 06:04:16 PM

Cancellation of the Actual (LOR2) condition in the South Australia region - 10 Sept 2016

AEMO ELECTRICITY MARKET NOTICE

Cancellation of the Actual (LOR2) condition in the South Australia region - 10 Sept 2016

Refer to AEMO Electricity Market Notice No. 54886

The Actual LOR2 condition in the South Australia Region is cancelled at 1805 hrs 10 Sept 2016


Manager NEM Real Time Operations
54888INTER-REGIONAL TRANSFER10/09/2016 06:03:47 PM

Inter regional transfer limit variation - Vic Region - 10 Sep 2016

AEMO ELECTRICITY MARKET NOTICE

Inter regional transfer limit variation - Vic Region - 10 Sep 2016

A planned outage of the Heywood No 2 500kV Bus in the Vic region was scheduled to be completed at 1000 hrs 11 Sep 2016 .

It was completed at 1759 hrs

See NOS for details.

The following constraints were invoked for this outage

F-I-HYSE
S-BOTH_BLKRG_C_OS
V-HYTX_M12
V-HY_500BUS
S-PA_VC_1

The outage constraints contain the following interconnectors on the LHS

V-S-MNSP1
V-SA

Manager NEM Real Time Operations
54887RECLASSIFY CONTINGENCY10/09/2016 04:42:51 PM

Reclassification of a Non-Credible Contingency Event: Tarong - Chinchilla 7183 and 7168 132 kV Lines in Queensland due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event: Tarong - Chinchilla 7183 and 7168 132 kV Lines in Queensland due to Lightning.

Lightning is occurring near the Tarong - Chinchilla 7183 and 7168 132 kV Lines.

AEMO considers the simultaneous trip of those circuits to now be more likely.
Therefore AEMO has reclassified this as a credible contingency event from 1640 hrs 10 sep 2016 until further notice.

Manager NEM Real Time Operations
54886RESERVE NOTICE09/09/2016 06:51:14 PM

Actual LOR2 South Australia Region - 09 Sept 2016

AEMO ELECTRICITY MARKET NOTICE

Actual LOR2 South Australia Region - 09 Sept 2016

Refer AEMO Electricity Market Notice 54872

An Actual LOR2 condition is declared for the South Australia region from 1800 hrs until further notice due to the planned outage of the Heywood No.2 500 kV busbar.

If a credible contingency event occurs during this period the South Australia region would separate from the rest of the NEM and is likely to result in interruptions to power supplies.

There are sufficient capacity reserves in the South Australia region to meet electricity demand but it may not be possible to bring the required additional capacity into service in time to avoid automatic under-frequency load shedding causing power interruptions.


Manager NEM Real Time Operations
54885NON-CONFORMANCE09/09/2016 05:00:17 PM

NON-CONFORMANCE Region NSW1 Friday, 9 September 2016

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 9 September 2016

AEMO declared a schedule generating unit non-conforming

Unit: VP5
Duration: 09/09/2016 16:40 to 09/09/2016 17:00
Amount: 17 MW
Constraint: NC-N_VP5

Auto-generated on behalf of Manager NEM Real Time Operations
54884RECLASSIFY CONTINGENCY09/09/2016 10:23:38 AM

Cancellation of the Reclassification of a Non-Credible Contingency Event: Dederang - Glenrowan No.1 and No.3 220 kV Lines in Victoria due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of the Reclassification of a Non-Credible Contingency Event: Dederang - Glenrowan No.1 and No.3 220 kV Lines in Victoria due to Lightning.

Refer AEMO Electricity Market Notice 54881

There is no longer any lightning activity in the vicinity of the Dederang - Glenrowan No.1 and No.3 220 kV Lines.

AEMO has cancelled the reclassification of the simultaneous trip of those circuits as a credible contingency event at 1025 hrs.

Constraint Set V-DDGN_N-2 revoked.


Manager NEM Real Time Operations
54883RESERVE NOTICE09/09/2016 10:14:43 AM

Cancellation of the Actual (LOR2) condition in the South Australia region - 09 Sept 2016

AEMO ELECTRICITY MARKET NOTICE

Cancellation of the Actual (LOR2) condition in the South Australia region- 09 Sept 2016

Refer to AEMO Electricity Market Notice No. 54882

The Actual LOR2 condition in the South Australia Region is cancelled at 0945 hrs 09 September 2016


Manager NEM Real Time Operations