Cancellation of Actual (LOR1) condition in the VIC region - 19/01/2018
EMO ELECTRICITY MARKET NOTICE
Cancellation of Actual (LOR1) condition in the VIC region - 19/01/2018
The Actual LOR1 Condition in the VIC Region advised in AEMO Electricity Market Notice No.60849 is cancelled at 1740 hrs 19/01/2018
Manager NEM Real Time Operations
Cancellation - Management of oscillations on the Terranora interconnector due to Non-physical Loss Runs.
Refer AEMO Electricity Market Notice 60842
Constraint Set #N-Q-MNSP1_E was revoked at 1730 hrs 19/01/2018.
This constraint set contains an equation with the following interconnector on the LHS.
N-Q-MNSP1
Manager NEM Real Time Operations
Management of South Australia Power System Security - Severe Weather Warning - 19/01/2018
Management of South Australia Power System Security - Severe Weather Warning - 19/01/2018
AEMO has determined that the severe weather warning issued by the BOM presents an added risk to the power system in South Australia.
To manage power system security, AEMO has applied a network constraint to limit the flow on the VIC-SA interconnector in the Victoria to South Australia direction.
The following constraint set was invoked at 1620 hrs and will remain in place until further notice.
I-VS_250
The constraint set contains equations with the following interconnectors on the LHS.
V-SA
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 19/01/2018
AEMO ELECTRICITY MARKET NOTICE
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 60846 is cancelled at 1530 hrs 19/01/2018.
No LOR2 condition is currently forecast in the PDPASA period.
Manager NEM Real Time Operations
[EventId:201801191545_NRM_VIC1_NSW1_stopped] NEGRES CONSTRAINT NRM_VIC1_NSW1 ceased operating from 19 January 2018 15:45
Issued by Australian Energy Market Operator Ltd at 1545 hrs on 19 January 2018
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 19 January 2018.
Refer to market notice: 60851
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to NSW directional interconnector.
The negative residue constraint NRM_VIC1_NSW1 ceased operating at 1545 hrs on 19 January 2018.
This is an AEMO autogenerated Market Notice.
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the VIC Region on 19/01/2018
The Forecast LOR2 condition in the VIC region advised in AEMO Electricity Market Notice No. 60845 is cancelled at 1530 hrs 19/01/2018.
No LOR2 condition is currently forecast in the PDPASA period.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Friday, 19 January 2018
NON-CONFORMANCE QLD1 Region Friday, 19 January 2018
AEMO declared a schedule generating unit non-conforming
Unit: TARONG#3
Duration: 19/01/2018 15:30 to 19/01/2018 15:40
Amount: 35 MW
Constraint: NC-Q_TARONG#3
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:201801191530_NRM_VIC1_NSW1_started] NEGRES CONSTRAINT NRM_VIC1_NSW1 started operating from 19 January 2018 15:30
Issued by Australian Energy Market Operator Ltd at 1530 hrs on 19 January 2018
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 19 January 2018.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to NSW directional interconnector.
The negative residue constraint set NRM_VIC1_NSW1 commenced operating from 1530 hrs on 19 January 2018.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:201801191500_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 19 January 2018 15:00
Issued by Australian Energy Market Operator Ltd at 1500 hrs on 19 January 2018
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 19 January 2018.
Refer to market notice: 60848
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1500 hrs on 19 January 2018.
This is an AEMO autogenerated Market Notice.