Reclassification of a Non-Credible Contingency Event: Collinsville - Stoney Creek No.7306 132 kV line and Collinsville - Newlands No.7121 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Collinsville - Stoney Creek No.7306 132 kV and Collinsville - Newlands No.7121 132 kV
Duration: 10/03/2020 14:20 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Collinsville North - Proserpine No.7125 132 kV line and Collinsville North - Proserpine No.7126 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Collinsville North - Proserpine No.7125 132 kV and Collinsville North - Proserpine No.7126 132 kV
Duration: 10/03/2020 14:20 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
RESERVE NOTICE MT PASA PUBLICATION 10 March 2020
Please note that MTPASA informs the market of potential reliability issues to allow the market to respond in the first instance, potentially avoiding the need for any market intervention or direction from AEMO.
For further information, please refer to:
https://www.aemo.com.au/Electricity/National-Electricity-Market-NEM/Data/Market-Management-System-MMS/Projected-Assessment-of-System-Adequacy
This notice supersedes Market Notice 74712 published on 02 February 2020.
Background
As part of a broader process of implementing the reliability standard, AEMO runs the Medium Term Projected Assessment of System Adequacy (MTPASA) process weekly to forecast expected unserved energy levels over a two year period. If the expected annual unserved energy exceeds the maximum level specified by the Reliability Standard, a Low Reserve Condition is identified.
For more information about how AEMO implements the reliability standard, please view the Reliability Standard Implementation Guidelines (RSIG) available on AEMO's website at
https://www.aemo.com.au/Electricity/National-Electricity-Market-NEM/Planning-and-forecasting/Reliability-Standard-Implementation-Guidelines
Forecasting
AEMO
Cancellation of a Non-Credible Contingency Event: Ross - Chalumbin No.857 275 kV line and Ross - Chalumbin No.858 275 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Ross - Chalumbin No.857 275 kV and Ross - Chalumbin No.858 275 kV
Cancellation time: 09/03/2020 22:14
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 74859
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Ross - Chalumbin No.857 275 kV line and Ross - Chalumbin No.858 275 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Ross - Chalumbin No.857 275 kV and Ross - Chalumbin No.858 275 kV
Duration: 09/03/2020 21:13 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Ross - Chalumbin No.857 275 kV line and Ross - Chalumbin No.858 275 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Ross - Chalumbin No.857 275 kV and Ross - Chalumbin No.858 275 kV
Cancellation time: 09/03/2020 18:39
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 74849
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV
Cancellation time: 09/03/2020 18:29
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 74848
Auto-generated on behalf of Manager NEM Real Time Operations
Update - Possible intervention to manage power system security in South Australia (SA) Region
Update - Possible intervention to manage power system security in South Australia (SA) Region
Refer AEMO Electricity Market Notice 74852
The synchronous generating units expected to be synchronised in SA from 2100 hrs 09/03/2020 to 1430 hrs 10/03/2020 in Pre-dispatch published at 1530 hrs 09/03/2020 are inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO currently estimates that, in the absence of sufficient market response by 1600 hrs 09/03/2020, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
Update - Possible intervention to manage power system security in South Australia (SA) Region
Update - Possible intervention to manage power system security in South Australia (SA) Region
Refer AEMO Electricity Market Notice 74850
The synchronous generating units expected to be synchronised in SA from 2100 hrs 09/03/2020 to 1330 hrs 10/03/2020 in Pre-dispatch published at 1500 hrs 09/03/2020 are inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO currently estimates that, in the absence of sufficient market response by 1600 hrs 09/03/2020, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations