Direction - SA Region - 12/03/2020
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).
The direction was necessary to maintain the power system in a secure operating state.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
The issue of the direction commences an AEMO intervention event.
AEMO declares all dispatch intervals during the event to be intervention dispatch intervals, commencing from the interval ending 0005 hrs on 13/03/2020.
Intervention pricing does not apply to this AEMO intervention event.
Manager NEM Real Time Operations
Possible intervention to manage power system security in South Australia (SA) Region
Possible intervention to manage power system security in South Australia (SA) Region
The synchronous generating units expected to be synchronised in SA from 0030 hrs 13 Mar 2020 to 1400 hrs 13 Mar 2020 in Pre-dispatch published at 0900hrs 12 Mar 2020 are inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO currently estimates that, in the absence of sufficient market response by 1700 hrs 12 Mar 2020, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Hazelwood - Rowville No.1 220kV line and Hazelwood - Rowville No.2 220kV line in VIC1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: VIC1
Lines: Hazelwood - Rowville No.1 220kV and Hazelwood - Rowville No.2 220kV
Cancellation time: 11/03/2020 23:44
Constraint set(s) revoked:
V-HWRO_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Refer AEMO Electricity Market Notice 74880
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Hazelwood - Rowville No.1 220kV line and Hazelwood - Rowville No.2 220kV line in VIC1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: VIC1
Lines: Hazelwood - Rowville No.1 220kV and Hazelwood - Rowville No.2 220kV
Duration: 11/03/2020 22:43 until further notice
Constraint set(s) invoked:
V-HWRO_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Goonyella - Nth Goonyella T- Stoney Creek 7122 132 kV line and Goonyella - Newlands No. 7155 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Goonyella - Nth Goonyella T- Stoney Creek 7122 132 kV and Goonyella - Newlands No. 7155 132 kV
Cancellation time: 11/03/2020 20:59
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 74878
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Goonyella - Nth Goonyella T- Stoney Creek 7122 132 kV line and Goonyella - Newlands No. 7155 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Goonyella - Nth Goonyella T- Stoney Creek 7122 132 kV and Goonyella - Newlands No. 7155 132 kV
Duration: 11/03/2020 19:57 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
CHG0058400: Pre-Prod SMP database servers maintenance activity
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Business to Business data exchange
Change Title: Pre-Prod SMP database servers maintenance activity
Change Start Date & Time: 12/03/2020 10:00:00 AEST
Change End Date & Time: 12/03/2020 11:00:00 AEST
Outage Start Date & Time: 12/03/2020 10:00:00 AEST
Outage End Date & Time: 12/03/2020 11:00:00 AEST
Change Description:
Outage of pre-production Electricity and Gas Hub systems for maintenance activities.
Environment: Pre-Production
Participant Impact and Requirements:
Electricity and Gas Hub systems will be unavailble briefly during the change window.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
NON-CONFORMANCE Region NSW1 Wednesday, 11 March 2020
NON-CONFORMANCE NSW1 Region Wednesday, 11 March 2020
AEMO declared a schedule generating unit non-conforming
Unit: VP6
Duration: 11/03/2020 06:45 to 11/03/2020 07:05
Amount: -14 MW
Constraint: NC-N_VP6
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Collinsville Nth-Clare Sth Tee King Creek 7128 132kV line and Strathmore-Clare South 7208 132kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Collinsville Nth-Clare Sth Tee King Creek 7128 132kV and Strathmore-Clare South 7208 132kV
Cancellation time: 10/03/2020 21:54
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 74873
Auto-generated on behalf of Manager NEM Real Time Operations