Market Notices

113392RECLASSIFY CONTINGENCY17/01/2024 08:24:30 PM

Cancellation of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Cancellation time: 17/01/2024 20:24

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 113390

Auto-generated on behalf of Manager NEM Real Time Operations
113390RECLASSIFY CONTINGENCY17/01/2024 07:21:01 PM

Reclassification of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Duration: 17/01/2024 19:20 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
113389RECLASSIFY CONTINGENCY17/01/2024 07:14:30 PM

Cancellation of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Cancellation time: 17/01/2024 19:14

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 113363

Auto-generated on behalf of Manager NEM Real Time Operations
113381PRICES SUBJECT TO REVIEW17/01/2024 07:05:16 PM

[EventId:202401171910_review] Prices for interval 17-Jan-2024 19:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1905 hrs on 17 January 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 17-Jan-2024 19:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
113380PRICES SUBJECT TO REVIEW17/01/2024 07:00:15 PM

[EventId:202401171905_review] Prices for interval 17-Jan-2024 19:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1900 hrs on 17 January 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 17-Jan-2024 19:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
113379PRICES SUBJECT TO REVIEW17/01/2024 06:55:19 PM

[EventId:202401171900_review] Prices for interval 17-Jan-2024 19:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1855 hrs on 17 January 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 17-Jan-2024 19:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
113378PRICES SUBJECT TO REVIEW17/01/2024 06:50:18 PM

[EventId:202401171855_review] Prices for interval 17-Jan-2024 18:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1850 hrs on 17 January 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 17-Jan-2024 18:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
113377PRICES SUBJECT TO REVIEW17/01/2024 06:45:11 PM

[EventId:202401171850_review] Prices for interval 17-Jan-2024 18:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1845 hrs on 17 January 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 17-Jan-2024 18:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
113376PRICES SUBJECT TO REVIEW17/01/2024 06:40:19 PM

[EventId:202401171845_review] Prices for interval 17-Jan-2024 18:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1840 hrs on 17 January 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 17-Jan-2024 18:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm