Market Notices

114577POWER SYSTEM EVENTS13/02/2024 01:22:13 PM

Significant power system event - 13 Feb 2024

AEMO ELECTRICITY MARKET NOTICE.

Significant power system event - 13 Feb 2024

At 1308 hrs 13/02/2024 a significant power system event occurred.

Description of event - Multiple tripping of generation and transmission lines in the Vic region

Transmission element(s) tripped - Moorabool Sydenham No1 and No2 500 kV lines tripped

Region/s - Vic

Load interrupted - in excess of 1000 MW

Generation volume tripped - 2300 MW

Updates will be provided as additional information becomes available.

This Market Notice is issued in accordance with NER clause 4.8.3.


Manager NEM Real Time Operations
114576PRICES SUBJECT TO REVIEW13/02/2024 01:20:23 PM

[EventId:202402131325_review] Prices for interval 13-Feb-2024 13:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1320 hrs on 13 February 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 13-Feb-2024 13:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
114575PRICES SUBJECT TO REVIEW13/02/2024 01:15:23 PM

[EventId:202402131320_review] Prices for interval 13-Feb-2024 13:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1315 hrs on 13 February 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 13-Feb-2024 13:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
- The Over-Constrained Dispatch process published on the AEMO website


This is an AEMO autogenerated Market Notice.
114567PRICES SUBJECT TO REVIEW13/02/2024 12:25:11 PM

[EventId:202402131230_review] Prices for interval 13-Feb-2024 12:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1225 hrs on 13 February 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 13-Feb-2024 12:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
114566PRICES SUBJECT TO REVIEW13/02/2024 12:20:18 PM

[EventId:202402131225_review] Prices for interval 13-Feb-2024 12:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1220 hrs on 13 February 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 13-Feb-2024 12:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
114565PRICES SUBJECT TO REVIEW13/02/2024 12:15:19 PM

[EventId:202402131220_review] Prices for interval 13-Feb-2024 12:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1215 hrs on 13 February 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 13-Feb-2024 12:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
114564PRICES SUBJECT TO REVIEW13/02/2024 12:11:25 PM

[EventId:202402131215_review] Prices for interval 13-Feb-2024 12:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1210 hrs on 13 February 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 13-Feb-2024 12:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
114563NON-CONFORMANCE13/02/2024 12:10:15 PM

NON-CONFORMANCE Region QLD1 Tuesday, 13 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 13 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 13/02/2024 12:05 to 13/02/2024 12:10
Amount: 15 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
114562PRICES SUBJECT TO REVIEW13/02/2024 12:05:17 PM

[EventId:202402131210_review] Prices for interval 13-Feb-2024 12:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1205 hrs on 13 February 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 13-Feb-2024 12:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm