Filter by category
Filter by Date
[EventId:202404081255_review] Prices for interval 08-Apr-2024 12:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1250 hrs on 8 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Apr-2024 12:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404081250_review] Prices for interval 08-Apr-2024 12:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1245 hrs on 8 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Apr-2024 12:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404081245_review] Prices for interval 08-Apr-2024 12:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1240 hrs on 8 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Apr-2024 12:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202404081240_review] Prices for interval 08-Apr-2024 12:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1235 hrs on 8 April 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Apr-2024 12:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Cancellation of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV
Cancellation time: 07/04/2024 16:44
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 116022
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV
Cancellation time: 07/04/2024 16:44
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 116021
Auto-generated on behalf of Manager NEM Real Time Operations
Direction - SA region 07/04/2024
Direction - SA region 07/04/2024
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).
The direction was necessary to maintain the power system in a secure operating state.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1705 hrs on 07/04/2024.
Intervention pricing does not apply to this AEMO intervention event.
Manager NEM Real Time Operations
Update - Possible intervention to manage power system security in SA region
Update - Possible intervention to manage power system security in SA region
Refer AEMO Electricity Market Notice 116015
The synchronous generating units currently expected to be synchronised in SA from 0900 hrs 08/04/2024 will be inadequate to maintain a secure operating state in SA .
AEMO estimates that, in the absence of sufficient market response by 1700 hrs 07/04/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV
Duration: 07/04/2024 14:38 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations