[EventId:202401160710_review] Prices for interval 16-Jan-2024 07:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 0705 hrs on 16 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jan-2024 07:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202401160705_review] Prices for interval 16-Jan-2024 07:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 0700 hrs on 16 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jan-2024 07:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202401160700_review] Prices for interval 16-Jan-2024 07:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 0655 hrs on 16 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jan-2024 07:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 18/01/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
[1.] From 1730 hrs 18/01/2024 to 2030 hrs 18/01/2024.
The forecast capacity reserve requirement is 870 MW.
The minimum capacity reserve available is 681 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 22/01/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1830 hrs to 1900 hrs 22/01/2024.
The forecast capacity reserve requirement is 1242 MW.
The minimum capacity reserve available is 1109 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 19/01/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1830 hrs to 1900 hrs 19/01/2024.
The forecast capacity reserve requirement is 1253 MW.
The minimum capacity reserve available is 1161 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 18/01/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1730 hrs to 2030 hrs 18/01/2024.
The forecast capacity reserve requirement is 1247 MW.
The minimum capacity reserve available is 985 MW.
AEMO Operations
[EventId:202401111300_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 11 January 2024 13:00
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 11 January 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 11 January 2024.
Refer to market notice: 113205
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1300 hrs on 11 January 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202401111205_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 11 January 2024 12:05
Issued by Australian Energy Market Operator Ltd at 1205 hrs on 11 January 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 11 January 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1205 hrs on 11 January 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.