[EventId:202402201815_review] Prices for interval 20-Feb-2024 18:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1810 hrs on 20 February 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 20-Feb-2024 18:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202402201810_review] Prices for interval 20-Feb-2024 18:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1805 hrs on 20 February 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 20-Feb-2024 18:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202402201805_review] Prices for interval 20-Feb-2024 18:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 20 February 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 20-Feb-2024 18:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Update to system strength constraints in North Queensland
Refer to market notice 110677
AEMO and Powerlink are continuing to investigate system strength requirements in North Queensland.
Due to commissioning of new feeder 8905 (H13 Ross - H39 Woree) 275kV line in Far North Queensland, the system normal system strength equations for low North Queensland demands and all Karreya stations out of service conditions have been revised.
A revision to the constraint equations will be implemented at 1400 hrs on Tuesday 20th February 2024.
The new system strength combinations have now published in a limits advice document on AEMO's website. For more information refer to the new limits advice: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice
This advice contains all the combinations for Queensland for system normal cases.
Below constraint equations in the Q-NIL set will be modified:
- Q_NIL_STRGTH_KBWF
- Q_NIL_STRGTH_KBWF_I
- Q_NIL_STRGTH_HAUSF
- Q_NIL_STRGTH_HAUSF_I
- Q_NIL_STRGTH_MEWF
- Q_NIL_STRGTH_MEWF_I
AEMO Operations
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 17/02/2024
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 17/02/2024
Refer Market Notice 114835
The AEMO Intervention Event and all associated directions are cancelled from 1530 hrs 18/02/2024
Manager NEM Real Time Operations
CHG0083624 | Completed | Production | A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Gas Hub
Change Title: A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0082609 | Completed | Production | MSATS-CATS Production Maintenance
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: MSATS-CATS Production Maintenance
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 16/02/2024
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 16/02/2024
Refer Market Notice 114818
The AEMO Intervention Event and all associated directions are cancelled from 1600 hrs 17/02/2024
Manager NEM Real Time Operations
Direction - SA region 17/02/2024
Direction - SA region 17/02/2024
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).
The direction was necessary to maintain the power system in a secure operating state.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1505 hrs on 17/02/2024.
Intervention pricing does not apply to this AEMO intervention event.
Manager NEM Real Time Operations