127508NON-CONFORMANCE12/06/2025 12:10:21 AM

NON-CONFORMANCE Region VIC1 Thursday, 12 June 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Thursday, 12 June 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: YWPS4
Duration: 12/06/2025 00:05 to 12/06/2025 00:10
Amount: 14 MW
Constraint: NC-V_YWPS4

Auto-generated on behalf of Manager NEM Real Time Operations
     
127505RESERVE NOTICE11/06/2025 07:43:29 PM

Cancellation of the Actual Lack Of Reserve Level 1 (LOR1) condition in the QLD Region on 11/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Actual LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 127504 is cancelled at 1945 hrs 11/06/2025.

Manager NEM Real Time Operations
     
127504RESERVE NOTICE11/06/2025 07:12:10 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 11/06/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 11/06/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1900 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs

The capacity reserve requirement is 730 MW
The minimum capacity reserve available is 693 MW

Manager NEM Real Time Operations
     
127474GENERAL NOTICE08/06/2025 12:12:12 AM

Network Augmentation Commissioned - NSW Region - 07/06/2025

AEMO ELECTRICITY MARKET NOTICE

A network augmentation has been commissioned in the NSW region at 2350 hrs 07/06/2025 as follows:

Culcairn Solar Farm substation has been cut into the existing Walla Walla - Wagga 6Y 330 kV Transmission Line to form the following circuits:

Culcairn - Walla Walla 6Y 330 kV Transmission Line
Walla Walla - Wagga 3G 330 kV Transmission Line

Manager NEM Real Time Operations
     
127433RESERVE NOTICE06/06/2025 07:56:10 PM

Correction - Cancellation of Actual (LOR1) condition in the NSW region - 06/06/2025

AEMO ELECTRICITY MARKET NOTICE

Correction - Cancellation of Actual (LOR1) condition in the NSW region - 06/06/2025

Correction to Market Notice 127432

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.127421 is cancelled at 1915 hrs 06/06/2025.

Manager NEM Real Time Operations
     
127432RESERVE NOTICE06/06/2025 07:12:56 PM

Cancellation of Actual (LOR1) condition in the NSW region - 06/06/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 06/06/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.127421 is cancelled at 1815 hrs 06/06/2025.

Manager NEM Real Time Operations
     
127421RESERVE NOTICE06/06/2025 05:39:13 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 06/06/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 06/06/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs

The capacity reserve requirement is 1694 MW
The minimum capacity reserve available is 1692 MW

Manager NEM Real Time Operations
     
127404NON-CONFORMANCE05/06/2025 08:10:13 PM

NON-CONFORMANCE Region QLD1 Thursday, 5 June 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 5 June 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 05/06/2025 19:30 to 05/06/2025 20:10
Amount: 23 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
127397RESERVE NOTICE04/06/2025 07:40:01 PM

Cancellation of Actual (LOR1) condition in the QLD region - 04/06/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 04/06/2025

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.127394 is cancelled at 1945 hrs 04/06/2025.