128190INTER-REGIONAL TRANSFER19/07/2025 07:35:53 PM

Inter-regional transfer limit variation - Eraring 500kV - Kemps Creek 5A2 500kV Line - NSW region - 19/07/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Eraring500kV - Kemps Creek 5A2 500kV Line - NSW region - 19/07/2025

At 1910 hrs 19/07/2025 there was a short notice outage of Eraring 500kV - Kemps Creek 5A2 500kV Line .

The following constraint set(s) invoked at 1920 hrs 19/07/2025
N-ERKC_ONE

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
128176INTER-REGIONAL TRANSFER19/07/2025 03:25:24 PM

Inter-regional transfer limit variation - Bulgana-Horsham 220kV LINE - VIC region - 19/07/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Bulgana-Horsham 220kV LINE - VIC region - 19/07/2025

A planned outage of Bulgana-Horsham 220kV LINE in the VIC region was scheduled from 0700 hrs 19/07/2025 to 1730 hrs 19/07/2025.

The outage has been completed and Bulgana-Horsham 220kV LINE returned to service at 1525 hrs 19/07/2025

Constraint set(s) revoked: V-BUHO

Manager NEM Real Time Operations
     
128175POWER SYSTEM EVENTS19/07/2025 01:35:42 PM

Non-credible contingency event - TAS region - 19/07/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - TAS region - 19/07/2025

At 1240 hrs the Liapoota - Wadamana - Palmerston 220 kV line and the Cattle Hill Wind Farm - Wadamana 220 kV line tripped.

AEMO did not instruct load shedding.

AEMO has been advised of a 70 MW load reduction at Nyrstar.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
     
128164INTER-REGIONAL TRANSFER18/07/2025 12:18:28 PM

Inter-regional transfer limit variation - S3 Greenbank 275 kV SVC - QLD region - 18/07/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - S3 Greenbank 275 kV SVC - QLD region - 18/07/2025

At 1207 hrs 18/07/2025 there was an unplanned outage of S3 Greenbank 275 kV SVC.

The following constraint set(s) invoked at 1215 hrs 18/07/2025
Q-GB_VC

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
128160POWER SYSTEM EVENTS18/07/2025 08:49:29 AM

Non-credible contingency event - QLD region - 18/07/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 18/07/2025

At 0825 hrs the H11_Nebo 275/132 kV No.1 Transformer was switched out on a planned outage and the H11_Nebo 275 kV SVC tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
     
128151INTER-REGIONAL TRANSFER17/07/2025 03:15:24 PM

Inter-regional transfer limit variation - Calvale-Halys 8810 275kV LINE - QLD region - 17/07/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Calvale-Halys 8810 275kV LINE - QLD region - 17/07/2025

A planned outage of Calvale-Halys 8810 275kV LINE in the QLD region was scheduled from 2300 hrs 15/07/2025 to 1600 hrs 18/07/2025.

The outage has been completed and Calvale-Halys 8810 275kV LINE returned to service at 1500 hrs 17/07/2025

Constraint set(s) revoked: Q-HACL

Manager NEM Real Time Operations
     
128149PRICES UNCHANGED16/07/2025 10:35:31 PM

[EventId:202507162215_confirmed] Prices for interval 16-Jul-2025 22:15 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2235 hrs on 16 July 2025

PRICES ARE NOW CONFIRMED for trading interval 16-Jul-2025 22:15.

In accordance with Market Notice 128139 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
128148PRICES UNCHANGED16/07/2025 10:35:22 PM

[EventId:202507162235_confirmed] Prices for interval 16-Jul-2025 22:35 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2235 hrs on 16 July 2025

PRICES ARE NOW CONFIRMED for trading interval 16-Jul-2025 22:35.

In accordance with Market Notice 128143 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
128147PRICES UNCHANGED16/07/2025 10:35:31 PM

[EventId:202507162230_confirmed] Prices for interval 16-Jul-2025 22:30 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2235 hrs on 16 July 2025

PRICES ARE NOW CONFIRMED for trading interval 16-Jul-2025 22:30.

In accordance with Market Notice 128142 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm