118489GENERAL NOTICE27/09/2024 09:51:41 PM

Network Augmentation Commissioned - NSW Region - 27/09/2024

AEMO ELECTRICITY MARKET NOTICE

A network augmentation has been commissioned in the NSW region at 2150 hrs 27/09/2024 as follows:

Walla Walla substation has been cut into the existing Wagga - Jinderra (62) 330 kV line to form the following circuits:

Jinderra - Walla Walla 62 330 kV Transmission Line
Walla Walla - Wagga 6Y 330 kV Transmission Line

Manager NEM Real Time Operations
     
118470RESERVE NOTICE26/09/2024 04:31:11 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 118449 has been updated at 1630 hrs to the following:

[1.] From 1630 hrs 26/09/2024 to 1930 hrs 26/09/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is {{LOR_U1.ReserveAvailable:962} MW.

Manager NEM Real Time Operations
     
118449RESERVE NOTICE26/09/2024 05:58:21 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 118448 has been updated at 0600 hrs to the following:

[1.] From 1730 hrs 26/09/2024 to 1930 hrs 26/09/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1203 MW.

Manager NEM Real Time Operations
     
118448RESERVE NOTICE26/09/2024 05:03:42 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 118440 has been updated at 0500 hrs to the following:

[1.] From 1800 hrs 26/09/2024 to 1900 hrs 26/09/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1221 MW.

Manager NEM Real Time Operations
     
118440RESERVE NOTICE25/09/2024 12:54:04 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1800 hrs 26/09/2024 to 1930 hrs 26/09/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1183 MW.

Manager NEM Real Time Operations
     
118438RESERVE NOTICE25/09/2024 06:47:42 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 25/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 118437 is cancelled at 0650 hrs 25/09/2024.

Manager NEM Real Time Operations
     
118437RESERVE NOTICE25/09/2024 05:44:32 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 25/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:

[1.] From 0700 hrs 25/09/2024 to 0730 hrs 25/09/2024.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 567 MW.

Manager NEM Real Time Operations
     
118436RESERVE NOTICE25/09/2024 04:00:57 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 25/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 118435 is cancelled at 0400 hrs 25/09/2024.

Manager NEM Real Time Operations
     
118435RESERVE NOTICE25/09/2024 02:42:31 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 25/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 118432 has been updated at 0230 hrs to the following:

[1.] From 0700 hrs 25/09/2024 to 0730 hrs 25/09/2024.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 592 MW.

Manager NEM Real Time Operations
     