Filter by category
Filter by Date
Inter-regional transfer limit variation - constraint automation to manage Power System Security in VIC region - 23/10/2024
In order to maintain the power system in a secure operating state in the VIC region, AEMO has invoked automated constraint set CA_SYDS_562A9792 from 0635 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
V-S-MNSP1
V-SA
VIC1-NSW1
Refer to AEMO Network Outage Scheduler (NOS) for further information.
Manager NEM Real Time Operations
Forecast Minimum System Load 1 (MSL1) in the VIC Region on 26/10/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region on 26/10/2024.
Minimum regional demand is forecast to be 1645 MW at 1300 hrs, and the advisory threshold is:
MSL1 - 1685 MW
MSL2 - 1185 MW
MSL3 - 685 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1230 hrs to 1300 hrs 26/10/2024.
AEMO Operations
Inter-regional transfer limit variation - Tamworth No 1 330 kV bus and Tamworth - Armidale No. 86 330 kV Line - NSW region - 19/10/2024
Tamworth No 1 330 kV bus and Tamworth - Armidale No. 86 330 kV Line - NSW region - 19/10/2024
A planned outage of Tamworth No 1 330 kV bus in the NSW region was scheduled from 1100 hrs 18/10/2024 to 1700 hrs 20/10/2024.
A planned outage of Tamworth - Armidale No. 86 330 kV Line in the NSW region was scheduled from 0500 hrs 09/10/2024 to 1700 hrs 20/10/2024.
The outage has been completed by 1250 hrs 19/10/2024.
Constraint set(s) invoked:
N-ARTW_86
N-LDTW_84
N-TW_SVC
N-TW_330_BUS1
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1
T-V-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Brinkworth- Red Hill- Bungama 132kV lines - SA region - 17/10/2024
Inter-regional transfer limit variation - Brinkworth- Red Hill- Bungama 132kV lines - SA region - 17/10/2024
At 1846 hrs 17/10/2024 there was an unplanned outage of Brinkworth- Red Hill- Bungama 132kV lines.
The following constraint set(s) invoked at 1855 hrs 17/10/2024
S-BRBG
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Hummocks - Bungama 132kV line - SA region - 17/10/2024
Inter-regional transfer limit variation - Hummocks - Bungama 132kV line - SA region - 17/10/2024
At 1842 hrs 17/10/2024 there was an unplanned outage of Hummocks - Bungama 132kV line.
The following constraint set(s) invoked at 1850 hrs 17/10/2024
S-HUBG
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Blyth West - Munno Para 275kV line- SA region - 17/10/2024
Inter-regional transfer limit variation - Blyth West - Munno Para 275kV line - SA region - 17/10/2024
At 1848 hrs 17/10/2024 there was an unplanned outage of Blyth West - Munno Para 275kV line.
The following constraint set(s) invoked at 1855 hrs 17/10/2024
S-BWMP
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the QLD region - 17/10/2024
Cancellation of Actual (LOR1) condition in the QLD region - 17/10/2024
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.118993 is cancelled at 1839 hrs 17/10/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 17/10/2024
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 17/10/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs
The capacity reserve requirement is 1136 MW
The minimum capacity reserve available is 1076 MW
Manager NEM Real Time Operations