Filter by category
Filter by Date
NON-CONFORMANCE Region SA1 Saturday, 31 August 2024
NON-CONFORMANCE SA1 Region Saturday, 31 August 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: STARHLWF
Duration: 31/08/2024 14:50 to 31/08/2024 15:25
Amount: 26 MW
Constraint: NC-S_STARHLWF
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Saturday, 31 August 2024
NON-CONFORMANCE NSW1 Region Saturday, 31 August 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: HILLSTN1
Duration: 31/08/2024 15:05 to 31/08/2024 15:20
Amount: 85 MW
Constraint: NC-N_HILLSTN1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Saturday, 31 August 2024
NON-CONFORMANCE SA1 Region Saturday, 31 August 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MANNSF2
Duration: 31/08/2024 11:45 to 31/08/2024 13:55
Amount: 7 MW
Constraint: NC-S_MANNSF2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 29 August 2024
NON-CONFORMANCE QLD1 Region Thursday, 29 August 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GSTONE2
Duration: 29/08/2024 15:35 to 29/08/2024 15:40
Amount: 28 MW
Constraint: NC-Q_GSTONE2
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-regional transfer limit variation - Dumaresq 330 kV SVC - NSW region - 28/08/2024
Inter-regional transfer limit variation - Dumaresq 330 kV SVC - NSW region - 28/08/2024
At 1125 hrs 28/08/2024 there was a short notice outage of Dumaresq 330 kV SVC.
The following constraint set(s) invoked at 1125 hrs 28/08/2024
N-DM_SVC
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 28/08/2024
In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA_SYDS_55E0E615 from 0900 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
N-Q-MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further information.
Manager NEM Real Time Operations
Update - Non-credible contingency event - VIC region - 28/08/2024
Update - Non-credible contingency event - VIC region - 28/08/2024
Refer AEMO Electricity Market Notice 117908
At 0134 hrs the APD No 2 Potline was returned to service.
At 0200 hrs the APD No 1 Potline was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - VIC region - 28/08/2024
Non-credible contingency event - VIC region - 28/08/2024
At 0001 hrs the APD No1 Potline and the APD No 2 Potline tripped.
AEMO did not instruct load shedding.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Cancellation - Inter-Regional Transfer limit variation - Murraylink 27/08/2024
Cancellation - Inter-Regional Transfer limit variation - Murraylink 27/08/2024
Refer AEMO Electricity Market Notice 117831
To manage power system security in the Victoria region, AEMO invoked the following network constraint.
Constraint Set invoked from 10:40 hrs 27/08/2024 to 11:00 hrs 27/08/2024
I:SVML_120
This constraint set contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Manager NEM Real Time Operations