Project Energy Connect (PEC-1) testing 12th November 2024 for flows in both directions
Refer to market notice 120016
There is an opportunity for testing Project Energy Connect (PEC-1) for flows in both directions up to 50 MW on 12th November from 06:00hrs to 11:00hrs
This test includes the synchronization of the new PEC Stage 1 interconnector and testing of the Phase Shifting transformer at Buronga substation.
Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.
Ben Blake
AEMO Operations
Inter-regional transfer limit variation - Bungama - Davenport 275 kV line - SA region - 11/11/2024
Inter-regional transfer limit variation - Bungama - Davenport 275 kV line - SA region - 11/11/2024
At 1307 hrs 11/11/2024 there was an unplanned outage of the Bungama - Davenport 275 kV line.
The following constraint set invoked at 1315 hrs 11/11/2024
S-BGDV
This constraint sets contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Saturday, 9 November 2024
NON-CONFORMANCE VIC1 Region Saturday, 9 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GANNB1
Duration: 09/11/2024 20:55 to 09/11/2024 21:10
Amount: 9 MW
Constraint: NC-V_GANNB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Saturday, 9 November 2024
NON-CONFORMANCE NSW1 Region Saturday, 9 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP5
Duration: 09/11/2024 02:40 to 09/11/2024 02:45
Amount: -42 MW
Constraint: NC-N_VP5
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 8 November 2024
NON-CONFORMANCE NSW1 Region Friday, 8 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 08/11/2024 12:30 to 08/11/2024 12:45
Amount: 16 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 8 November 2024
NON-CONFORMANCE NSW1 Region Friday, 8 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BHB1
Duration: 08/11/2024 09:15 to 08/11/2024 10:10
Amount: 25 MW
Constraint: NC-N_BHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 7 November 2024
NON-CONFORMANCE NSW1 Region Thursday, 7 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 07/11/2024 14:35 to 07/11/2024 15:05
Amount: -32 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 7 November 2024
NON-CONFORMANCE NSW1 Region Thursday, 7 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 07/11/2024 09:00 to 07/11/2024 10:45
Amount: -50 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations