114686INTER-REGIONAL TRANSFER14/02/2024 01:24:53 AM

Inter-regional transfer limit variation: Moorabool - Sydenham No1 and No2 500 kV lines - VIC region - 13/02/2024 -

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation: Moorabool - Sydenham No1 and No2 500 kV lines - 13/02/2024

At 1308 hrs 13/02/2024 the Moorabool - Sydenham No1 and No2 500 kV lines tripped.

Refer Market notices 114577 and 114625.

The following constraint set(s) are invoked :

V-X_MLSY
F-V-X_ML_BUSTIE_500
I-VS_050

These constraint set contains equations with the following interconnectors on the LHS.

T-V-MNSP1
V-SA
V-S-MNSP1
VIC1- NSW1

Refer to the Network outage scheduler (NOS) for more details:

Manager NEM Real Time Operations
114537RESERVE NOTICE12/02/2024 04:17:59 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 13/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 114532 is cancelled at 1613 hrs 12/02/2024.

Manager NEM Real Time Operations
114532RESERVE NOTICE12/02/2024 02:51:08 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 13/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1630 hrs 13/02/2024 to 1900 hrs 13/02/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1097 MW.


Manager NEM Real Time Operations
114520RESERVE NOTICE12/02/2024 09:12:01 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region [beginning] on 12/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 114519 is cancelled at 0910 hrs 12/02/2024.

Manager NEM Real Time Operations
114519RESERVE NOTICE12/02/2024 05:47:03 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 12/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1730 hrs 12/02/2024 to 1800 hrs 12/02/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1389 MW.


Manager NEM Real Time Operations
114517RESERVE NOTICE12/02/2024 03:10:37 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 13/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 114502 is cancelled at 1500 hrs 12/02/2024

[No LOR 1 condition is currently forecast in the STPASA period.]

Manager NEM RTO
114502RESERVE NOTICE11/02/2024 02:38:43 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 13/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 114472 has been updated at 1430 hrs 11/02/2024 to the following:

[1.] From 1530 hrs 13/02/2024 to 1600 hrs 13/02/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1281 MW.

[2.] From 1630 hrs 13/02/2024 to 1730 hrs 13/02/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1320 MW.


Manager NEM Real Time Operations
114472RESERVE NOTICE10/02/2024 02:43:22 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 13/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 114455 has been updated at 1430 hrs 10/02/2024 to the following:

[1.] From 1530 hrs 13/02/2024 to 1700 hrs 13/02/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1196 MW.

[2.] From 1730 hrs 13/02/2024 to 1800 hrs 13/02/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1359 MW.


Manager NEM Real Time Operations
114455RESERVE NOTICE09/02/2024 02:41:13 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 13/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

1. From 1730 to 1800 hrs 13/02/2024.
The forecast capacity reserve requirement is 1612 MW.
The minimum capacity reserve available is 1517 MW.

2. From 1830 to 1900 hrs 13/02/2024.
The forecast capacity reserve requirement is 1703 MW.
The minimum capacity reserve available is 1656 MW.


AEMO Operations