Filter by category
Filter by Date
Inter-regional transfer limit variation - Southpine - Rocklea 809 275 kV Line - QLD region - 18/11/2024
Inter-regional transfer limit variation - Southpine - Rocklea 809 275 kV Line - QLD region - 18/11/2024
At 1545 hrs 18/11/2024 there was an unplanned outage of Southpine - Rocklea 809 275 kV Line.
The following constraint set(s) invoked at 1545 hrs 18/11/2024
Q-RLSP_809
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
[EventId:202411181530_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 18 November 2024 15:30
Issued by Australian Energy Market Operator Ltd at 1530 hrs on 18 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 18 November 2024.
Refer to market notice: 120613
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1530 hrs on 18 November 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202411181400_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 18 November 2024 14:00
Issued by Australian Energy Market Operator Ltd at 1400 hrs on 18 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 18 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1400 hrs on 18 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202411172035_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 17 November 2024 20:35
Issued by Australian Energy Market Operator Ltd at 2035 hrs on 17 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 17 November 2024.
Refer to market notice: 120561
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2035 hrs on 17 November 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202411171605_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 17 November 2024 16:05
Issued by Australian Energy Market Operator Ltd at 1605 hrs on 17 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 17 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1605 hrs on 17 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Inter-regional transfer limit variation - Armidale to Dumaresq (8C) 330 kV line - NSW region - 17/11/2024
Inter-regional transfer limit variation - Armidale to Dumaresq (8C) 330 kV line - NSW region - 17/11/2024
A planned outage of Armidale to Dumaresq (8C) 330 kV line in the NSW region was scheduled from 0500 hrs 17/11/2024 to 1700 hrs 17/11/2024.
The outage has been completed returned to service at 1330 hrs 17/11/2024
Constraint set(s) revoked:
N-ARDM_8C
N-DM_SVC
N-TW_SVC
N-X_8C+DM+TW_SVC
Manager NEM Real Time Operations
[EventId:202411161200_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 16 November 2024 12:00
Issued by Australian Energy Market Operator Ltd at 1200 hrs on 16 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 16 November 2024.
Refer to market notice: 120523
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1200 hrs on 16 November 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202411160905_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 16 November 2024 09:05
Issued by Australian Energy Market Operator Ltd at 0905 hrs on 16 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 16 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0905 hrs on 16 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202411151955_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 15 November 2024 19:55
Issued by Australian Energy Market Operator Ltd at 1955 hrs on 15 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 November 2024.
Refer to market notice: 120505
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1955 hrs on 15 November 2024.
This is an AEMO autogenerated Market Notice.