Inter-regional transfer limit variation -Liddell - Tomago 82 330kV Line - NSW region - 22/04/2024
Inter-regional transfer limit variation - Liddell - Tomago 82 330kV Line - NSW region - 22/04/2024
A planned outage of Liddell - Tomago 82 330kV Line in the NSW region was scheduled from 0600 hrs 03/04/2024 to 1700 hrs 22/04/2024.
The outage has been completed and Liddell - Tomago 82 330kV Line returned to service at 1450 hrs 22/04/2024
Constraint set(s) revoked: N-LDTM_82_OPEN
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Farrell - Sheffield Nos 1 and 2 220kV Lines - TAS region - 22/04/2024
Inter-regional transfer limit variation - Farrell - Sheffield Nos 1 and 2 220kV Lines - TAS region - 22/04/2024
At 1315 hrs 22/04/2024 there was an unplanned outage of Farrell - Sheffield Nos 1 and 2 220kV Lines.
The following constraint set(s) invoked at 1315 hrs 22/04/2024
T-X_FASH_C
This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
CHG0088138 | Completed | Production | Brisbane MarketNet Firewall Refresh
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Firewall
Change Title: Brisbane MarketNet Firewall Refresh
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0088121 | Completed | Production | Production MSATS Lifecycle Maintenance
Change Number: CHG0088121
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Production MSATS Lifecycle Maintenance
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Inter-regional transfer limit variation - Tailem Bend 275 kV Capacitor - SA region - 19/04/2024
Inter-regional transfer limit variation - Tailem Bend 275 kV Capacitor - SA region - 19/04/2024
At 2341 hrs 19/04/2024 there was an unplanned outage of the Tailem Bend 275 kV Capacitor.
The following constraint set(s) invoked at 0005 hrs 20/04/2024
S-TBCP1
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Murraylink interconnector - VIC and SA regions - 19/04/2024
Inter-regional transfer limit variation - Murraylink interconnector - VIC and SA regions - 19/04/2024
A planned outage of Murraylink interconnector was scheduled from 0800 hrs 24/03/2024 to 1700 hrs 27/04/2024.
The outage has been completed and Murraylink interconnector returned to service at 1710 hrs 19/04/2024
Constraint set(s) revoked: I-MURRAYLINK
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
CHG0088386 | Production | QLD Internet Router Refresh
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Internet Access
Change Title: QLD Internet Router Refresh
Change Start Date & Time: 04/05/2024 09:00:01 AEST
Change End Date & Time: 04/05/2024 14:00:01 AEST
Outage Start Date & Time: 04/05/2024 09:30:32 AEST
Outage End Date & Time: 04/05/2024 12:30:32 AEST
Environment: Production
Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage:
IPWAN Participants - Nil
Lan-2-Lan VPN Participants (IPSEC) - Up to 2 hour outage for participants who have established their VPN connection/s via the AEMO QLD datacenter termination point (202.44.76.10) only - All L2L connections should be established to both QLD / NSW.
Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO NSW datacenter termination point (202.44.78.10) prior to this scheduled outage.
B2B VPN - Up to 2 hour outage to TNSPs with B2B VPN to AEMO QLD Datacentre if VPN connection is only terminating in QLD only
SSL VPN Participants: None expected as DNS entry will be updated to remove QLD IP.
GASHUB: No impact is expected as GASHUB is currently operating out of NOR Datacenter.
Other Impacts will have been communicated in advance.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0088831 | Production | Identity Service Config Update in Production.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Identity Service (IDS)
Change Title: Identity Service Config Update in Production.
Change Start Date & Time: 22/04/2024 12:00:53 AEST
Change End Date & Time: 22/04/2024 14:30:01 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: Brief loss of redundancy might be noticed for users using Markets portal , between 12:30 PM and 13:00 PM.
Identity Service is used by the following systems:
*MSATS
*APIs (EMMS, GBB, MSATS)
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0088421 | Production | A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Gas Hub
Change Title: A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.
Change Start Date & Time: 05/05/2024 09:00:00 AEST
Change End Date & Time: 05/05/2024 17:00:00 AEST
Outage Start Date & Time: 05/05/2024 10:00:00 AEST
Outage End Date & Time: 05/05/2024 14:00:00 AEST
Environment: Production
Participant Impact and Requirements: The following impacts are expected during this maintenance:
- All access to the Electricity B2B Hub will be unavailable.
- All access to the Gas B2B Hub and all ebXML gateways (AEMOMIBB, AGNLGWY, LVI & VENCORP) will be unavailable. CATS and MDMT transactions for VIC/QLD will be delayed during the maintenance window.
- Users are not required to take any action due to this change, however will need to enact manual workarounds for the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities.