Filter by category
Filter by Date
Reclassification of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV
Duration: 16/01/2024 12:51 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 15/01/2024
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 15/01/2024
Refer Market Notice 113275
The AEMO Intervention Event and all associated directions are cancelled from 1300 hrs 16/01/2024
Manager NEM Real Time Operations
Update - Possible intervention to manage power system security in SA region
Update - Possible intervention to manage power system security in SA region
Refer AEMO Electricity Market Notice 113307
The synchronous generating units currently expected to be synchronised in SA from 2300 hrs 16/01/2024 will be inadequate to maintain a secure operating state in SA .
AEMO estimates that, in the absence of sufficient market response by 1400 hrs 16/01/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
Reclassification of Non-Credible Contingency Event : Tungkillo- Robertstown No.1 and No.2 275kV lines and the Robertstown No.1 and No.2 synchronous condensers in SA region due to Lightning
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to be more likely and reasonably possible. Accordingly AEMO has reclassified it as credible contingency event.
Region: SA1
Elements: Tungkillo- Robertstown No.1 and No.2 275kV lines and the Robertstown No.1 and No.2 synchronous condensers
Duration: 16/01/2024 12:40 hrs until further notice
Constraint set(s) revoked: S-RBTU+SCON_N-2
Constraint set contains the following interconnector(s) on the left hand side:
V-S-MNSP1
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Ross - Chalumbin No.857 275 kV line and Ross - Chalumbin No.858 275 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Ross - Chalumbin No.857 275 kV and Ross - Chalumbin No.858 275 kV
Duration: 16/01/2024 12:31 until further notice
Constraint set(s) invoked:
Q-RSCH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Possible intervention to manage power system security in South Australia (SA) Region
Possible intervention to manage power system security in South Australia (SA) Region
The synchronous generating units currently expected to be synchronised in SA from 2300 hrs 16/01/2024 will be inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
[EventId:202401160715_confirmed] Prices for interval 16-Jan-2024 07:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0735 hrs on 16 January 2024
PRICES ARE NOW CONFIRMED for trading interval 16-Jan-2024 07:15.
In accordance with Market Notice 113292 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202401160735_confirmed] Prices for interval 16-Jan-2024 07:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0735 hrs on 16 January 2024
PRICES ARE NOW CONFIRMED for trading interval 16-Jan-2024 07:35.
In accordance with Market Notice 113298 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202401160730_confirmed] Prices for interval 16-Jan-2024 07:30 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0735 hrs on 16 January 2024
PRICES ARE NOW CONFIRMED for trading interval 16-Jan-2024 07:30.
In accordance with Market Notice 113296 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.