[EventId:202401301920_review] Prices for interval 30-Jan-2024 19:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1915 hrs on 30 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 30-Jan-2024 19:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202401301915_review] Prices for interval 30-Jan-2024 19:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1910 hrs on 30 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 30-Jan-2024 19:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202401301910_review] Prices for interval 30-Jan-2024 19:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1905 hrs on 30 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 30-Jan-2024 19:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Update - Direction - SA Region - 28/01/2024
Update - Direction - SA Region - 28/01/2024
Refer Market Notice 113930
The AEMO intervention event that commenced from interval ending 1705 hrs on 28/01/2024 is continuing.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/02/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1700 hrs to 1900 hrs 06/02/2024.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 476 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
CHG0082787 | Completed | Pre-Production | Pre-Production MSATS r50.0.5 Patch Release
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Production MSATS r50.0.5 Patch Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 01/02/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113977 is cancelled at 1500 hrs 29/01/2024.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 01/02/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113968 has been updated at 1400 hrs 29/01/2024 to the following:
From 0800 hrs to 1400 hrs 01/02/2024.
The forecast capacity reserve requirement is 910 MW.
The minimum capacity reserve available is 29 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Update - Direction - SA Region - 28/01/2024
Update - Direction - SA Region - 28/01/2024
Refer Market Notice 113930
The AEMO intervention event that commenced from interval ending 1705 hrs on 28/01/2024 is continuing.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations