PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region [beginning] on 01/07/2024
The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No.117253 is cancelled at 0915 hrs 01/07/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 01/07/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the TAS region for the following period:
[1.] From 0900 hrs 01/07/2024 to 1000 hrs 01/07/2024.
The forecast capacity reserve requirement is 686 MW.
The minimum capacity reserve available is 626 MW.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region beginning on 02/07/2024
The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 117249 has been updated at 1420 hrs 30/06/2024 to the following:
[1.] From 0800 hrs 02/07/2024 to 0830 hrs 02/07/2024.
The forecast capacity reserve requirement is 646 MW.
The minimum capacity reserve available is 644 MW.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region beginning on 02/07/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the TAS region for the following periods:
[1.] From 0800 hrs 02/07/2024 to 0830 hrs 02/07/2024.
The forecast capacity reserve requirement is 646 MW.
The minimum capacity reserve available is 637 MW.
[2.] From 0800 hrs 03/07/2024 to 0830 hrs 03/07/2024.
The forecast capacity reserve requirement is 646 MW.
The minimum capacity reserve available is 637 MW.
Manager NEM Real Time Operations
[EventId:202406271800_review] Prices for interval 27-Jun-2024 18:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1755 hrs on 27 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Jun-2024 18:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406271755_review] Prices for interval 27-Jun-2024 17:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1750 hrs on 27 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Jun-2024 17:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406271750_review] Prices for interval 27-Jun-2024 17:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1745 hrs on 27 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Jun-2024 17:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406271745_review] Prices for interval 27-Jun-2024 17:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1740 hrs on 27 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Jun-2024 17:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406271740_review] Prices for interval 27-Jun-2024 17:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 27 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Jun-2024 17:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.