Filter by category
Filter by Date
Cancellation of the Actual Lack Of Reserve Level 1 (LOR1) condition in the QLD Region on 11/06/2025
The Actual LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 127504 is cancelled at 1945 hrs 11/06/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 11/06/2025
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 11/06/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1900 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 730 MW
The minimum capacity reserve available is 693 MW
Manager NEM Real Time Operations
Network Augmentation Commissioned - NSW Region - 07/06/2025
A network augmentation has been commissioned in the NSW region at 2350 hrs 07/06/2025 as follows:
Culcairn Solar Farm substation has been cut into the existing Walla Walla - Wagga 6Y 330 kV Transmission Line to form the following circuits:
Culcairn - Walla Walla 6Y 330 kV Transmission Line
Walla Walla - Wagga 3G 330 kV Transmission Line
Manager NEM Real Time Operations
[EventId:202506071630_review] Prices for interval 07-Jun-2025 16:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1625 hrs on 7 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 07-Jun-2025 16:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506071625_review] Prices for interval 07-Jun-2025 16:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1620 hrs on 7 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 07-Jun-2025 16:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506071620_review] Prices for interval 07-Jun-2025 16:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1615 hrs on 7 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 07-Jun-2025 16:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506071615_review] Prices for interval 07-Jun-2025 16:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1610 hrs on 7 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 07-Jun-2025 16:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506071610_review] Prices for interval 07-Jun-2025 16:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1605 hrs on 7 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 07-Jun-2025 16:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506071605_review] Prices for interval 07-Jun-2025 16:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1600 hrs on 7 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 07-Jun-2025 16:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.