55064SETTLEMENTS RESIDUE30/09/2016 05:35:17 AM

[EventId:201609300535_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 30 September 2016 05:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0535 hrs on 30 September 2016

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 30 September 2016.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 0535 hrs on 30 September 2016.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
55063SETTLEMENTS RESIDUE30/09/2016 05:15:19 AM

[EventId:201609300515_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 30 September 2016 05:15

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0515 hrs on 30 September 2016

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 30 September 2016.

Refer to market notice: 55062

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 0515 hrs on 30 September 2016.

This is an AEMO autogenerated Market Notice.
55062SETTLEMENTS RESIDUE30/09/2016 04:10:19 AM

[EventId:201609300410_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 30 September 2016 04:10

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0410 hrs on 30 September 2016

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 30 September 2016.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 0410 hrs on 30 September 2016.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
55059SETTLEMENTS RESIDUE30/09/2016 02:45:24 AM

[EventId:201609300245_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 30 September 2016 02:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0245 hrs on 30 September 2016

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 30 September 2016.

Refer to market notice: 55058

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 0245 hrs on 30 September 2016.

This is an AEMO autogenerated Market Notice.
55058SETTLEMENTS RESIDUE30/09/2016 02:05:28 AM

[EventId:201609300205_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 30 September 2016 02:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0205 hrs on 30 September 2016

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 30 September 2016.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 0205 hrs on 30 September 2016.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
55039SETTLEMENTS RESIDUE29/09/2016 03:45:26 PM

[EventId:201609291545_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 29 September 2016 15:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1545 hrs on 29 September 2016

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 29 September 2016.

Refer to market notice: 55038

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1545 hrs on 29 September 2016.

This is an AEMO autogenerated Market Notice.
55038SETTLEMENTS RESIDUE29/09/2016 03:05:29 PM

[EventId:201609291505_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 29 September 2016 15:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1505 hrs on 29 September 2016

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 29 September 2016.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1505 hrs on 29 September 2016.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
55034SETTLEMENTS RESIDUE29/09/2016 10:20:21 AM

[EventId:201609291020_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 29 September 2016 10:20

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1020 hrs on 29 September 2016

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 29 September 2016.

Refer to market notice: 55032

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1020 hrs on 29 September 2016.

This is an AEMO autogenerated Market Notice.
55032SETTLEMENTS RESIDUE29/09/2016 09:00:17 AM

[EventId:201609290900_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 29 September 2016 09:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0900 hrs on 29 September 2016

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 29 September 2016.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 0900 hrs on 29 September 2016.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.